EXECUTIVE
SUMMARY
4. Summary
of Complaints, Notification of Summons and Prosecutions20
7. Conclusion
and Recommendations24
List of Appendices
A. Alignment and Works Area for the Contract No. HY/2014/08
B. Construction Programme
C. Project Organization Chart
D. Dust Event-Action Plan (EAP)
E. Noise Event-Action Plan (EAP)
F. Environmental Mitigation Implementation Schedule (EMIS)
G. Monitoring
Schedules of the Reporting Month
H. Calibration
Certificate (Air Monitoring)
I. Calibration
Certificate (Noise)
J. The
Certification of Laboratory with HOKLAS Accredited Analytical Tests
K. Location
Plan of Noise and Air Quality Monitoring Station
L. Monitoring
Data (Air Monitoring)
M.
Monitoring Data (Noise)
N. Waste
Flow Table
O. Statistics
on Complaint, Notifications of Summons and Successful
Prosecutions
P. Monitoring
Schedule of the Coming Month
Q. Interim
Report for the Complaint
Executive Summary
A.1 Build King – SKEC Joint Venture (“Contractor”) commenced the construction works of Highway Department (HyD) Central Kowloon Route Contract No. HY/2014/08 – Section of Yau Ma Tei East (“The Project”) on 20 April 2018. This is the 34th monthly Environmental Monitoring and Audit (EM&A) report presenting the EM&A works carried out during the period from 1 January 2021 to 31 January 2021.
A.2
A summary of the construction
works reported by Main Contractor for the Project during the reporting month is
listed below. \
Construction Activities undertaken |
·
Install 406mm pipe piles at Yau Ma Tei Police
Station (YMTPS) ·
Construction of D-wall panels (31 panels) at Zone B ·
Site formation, predrilling, remedial works for land
contamination, grout curtain wall & guide wall & D-wall at Zone B ·
Construction of Stage 3 D-wall panels, soil improvement works, sheet
piling at Zone C ·
Demolition of Yau Ma Tei
Specialist Clinic Extension (YMTSCE) building including substructure removal ·
Demolition of Car Park Building including Advance Works and
Substructure Removal ·
Guide
wall, D-wall and pipe piles at Zone D ·
Predrilling,
pipe piles & TTA Stage 4 at Zone G1 (Stage 1) ·
ELS, Excavation and Construction of Pad Footing, Piers and Portal
Frame for Reprovision of Gascoigne Road Flyover
(RGRF) ·
CLP Cable Diversion, demolition of subway/ backfill & predrilling
at Zone D |
A.3
A summary of regular construction noise and
construction dust monitoring activities in this reporting period is listed
below:
Regular construction noise
monitoring during normal working hours
W-N1A W-N18, W-N25A W-P11 W-P11-T |
5 times 4 times 4 times 1 time |
Construction dust (24-hour TSP)
monitoring
W-A1 |
5 times |
W-A6 |
4 times |
Construction dust (1-hour TSP)
monitoring
W-A1 |
15 times |
|
W-A6 |
12 times |
|
A.4
Noise monitoring at the Coronation Tower 1
(W-P11) was temporarily suspended on 27 January 2021 due to a case of novel
coronavirus infection at the Coronation Circle on 17 January 2021. Temporary
alternative noise monitoring location, W-P11-T was used to conduct noise
monitoring on 27 January 2021. Details of temporary alternative monitoring
location are presented in Temporary Alternative Proposal for Monitoring Station
as proposed by ET and agreed by IEC dated 27 March 2020. On the other hand, the
Government had expanded the specified areas for
compulsory COVID-19 testing on 26 January 2021. The specified areas were
recognized as high risk areas. TSP monitoring at Man
Cheong Building (W-A6), noise monitoring at Hydan
Place (W-N18), and noise monitoring at Prosperous Garden Block 1
(W-N25A/W-N25A-T) were temporarily suspended from 27 January 2021 to 9 February
2021 as these stations were located inside or in proximity to the specified
areas.
A.5 Bi-weekly inspection of the implementation of landscape and visual mitigation measures was conducted on 14, 28 January 2021. Details of the audit findings and implementation status are presented in Section 5.
A.6 Joint weekly site inspections were conducted by representatives of Environmental Team (ET), Contractor and Engineer on 7, 14, 21, 28 January 2021. One joint site inspection with IEC was also undertaken on 14 January 2021. Details of the audit findings and implementation status are presented in Section 5.
A.7
Details of waste management are
presented in Section 3.
A.8
One Action Level of
construction noise was triggered during the reporting period as there was one
documented complaint received on 28 January 2021 related to construction noise
at Zone D2 and D3. No exceedance of Limit Level of construction noise was
recorded in the reporting month. No exceedance of the Action Level and Limit
Levels of 24-hour TSP and 1-hour TSP was recorded during the reporting month.
A.9
One noise-related complaint was received in
the reporting month on 28 January 2021. After investigation with Contractor,
precautionary measures had been proposed to the Contractor by ET. The interim
report for the complaint is shown in Appendix Q.
A.10
No non-compliance was reported in the
reporting month.
A.11
No notification of summon
or prosecution was received in this reporting month.
A.12
A summary of the construction activities provided
by Main Contractor in the next reporting month is listed below:
Construction Activities to be undertaken |
·
Removal of remaining waling and struts at Zone A ·
Continue for D-wall construction at Zone B ·
Predrilling works, utilities diversion works, site formation works,
guide wall, pre-boring works and D-wall construction at Zone B. ·
Phase 3 Works (Construction of New Refuse Collection Area) for
Methadone Clinic ·
Continue for D-wall construction,
Underpinning Works for existing Piers, CLP cable diversion at Zone C ·
Works for GRF at HKAA area: carry out ELS part B and pad footing construction
and pier construction. ·
Continue for advance works (covered walkway erection, liaison/PR works, removal
of asbestos and furniture) for demolition works at carpark building ·
Continue for outstanding works for Phase 2 at Temporary Public Library
Cum Jade Hawker Bazaar Building (TPLCJHB) and complete decantation of
existing JHB ·
CLP cable diversion, predrilling works, demolition of subway,
backfilling of subway at removal of trees (pending tree felling permit), site
formation works of zone 3 for noise enclosure works ·
Implement TTA along Ferry Street to commence predrilling works at west
side of Zone 3 Noise Enclosure ·
Continue pre-coring works, pipe piling works and commence D-wall construction at Zone D ·
Commence
Pipe Piles installation at Zone G1 (Stage 1) ·
Implement
TTA Stage 3 to facilitate works along Kansu Street ·
Monitoring of instrumentation for all areas |
|
1.
Basic
Project Information
1.1. Central Kowloon Route (CKR) is a 4.7 km long dual 3-lane trunk road in Central Kowloon linking Yau Ma Tei Interchange in West Kowloon with the road network on Kai Tak Development and Kowloon Bay in East Kowloon.
1.2. The Central Kowloon Route – Design and Construction Environmental Impact Assessment Report (Register No.: AEIAR-171/2013) was approved with conditions by the Environmental Protection Department (EPD) on 11 July 2013. An Environmental Permit (EP 457/2013) was issued on 9 August 2013. Variations of EP (VEP) was subsequently applied for and the latest EP (EP-457/2013/C) was issued by EPD on 16 January 2017. A Further EP (FEP-02/457/2013/C) was issued by EPD on 5 March 2018.
1.3. The construction of the CKR had been divided into different sections. This Contract No. HY/2014/08 – Section of Yau Ma Tei East (YMTE) covers part of the construction activities located at Yau Ma Tei under the EP and FEP which includes:
Section of Yau Ma Tei East
ii. Construction and subsequent handover of Yau Ma Tei Access Shaft for facilitating the access and use by the contractor of Central Kowloon Route - Central Tunnel contract
iii. Demolition of existing buildings including Yau Ma Tei Multi-storey Carpark Building, Yau Ma Tei Specialist Clinic Extension Building and Yau Ma Tei Jade Hawker Bazaars
iv. Demolition and re-provisioning of Gascoigne Road Flyover(GRF) and the underpinning works for the existing Ferry Street Flyover and Yau Ma Tei Police Station New Wing Building
vi. Design and construction of Noise Barrier Works
The alignment
and works area for the Contract No. HY/2014/08 - are shown
in Appendix A.
1.4. A summary of the major construction activities undertaken in this reporting period is shown in Table 1.1. The construction programme is presented in Appendix B.
Table 1.1 Summary of the Construction Activities
reported by Main Contractor during the Reporting Month
Construction Activities
undertaken |
·
Install 406mm pipe piles at YMTPS ·
Construction of D-wall panels (31 panels) at Zone B ·
Site formation, predrilling, remedial works for land
contamination, grout curtain wall & guide wall & D-wall at Zone B ·
Construction of Stage 3 D-wall panels, soil improvement works, sheet
piling at Zone C ·
Demolition of YMTSCE building including substructure removal ·
Demolition of Car Park Building including Advance Works and
Substructure Removal ·
Guide
wall, D-wall and pipe piles at Zone D ·
Predrilling,
pipe piles & TTA Stage 4 at Zone G1 (Stage 1) ·
ELS, Excavation and Construction of Pad Footing, Piers and Portal
Frame for RGRF ·
CLP Cable Diversion, demolition of subway/ backfill & predrilling
at Zone D |
1.5. The project organisational chart specifying management structure and contact details are shown in Appendix C.
Table 1.2 Summary of the Status of Valid Environmental Licence
Notification, Permit and Documentations
Permit/ Licences/ Notification /Reference No. |
Valid Period |
Status |
Remark |
|
From |
To |
|||
Environmental Permit |
||||
EP-457/2013/C |
23 Apr 2019 |
End of Project |
Valid |
- |
Further Environmental Permit |
||||
FEP-02/457/2013/C |
5 Mar2018 |
End of Project |
Valid |
|
Wastewater Discharge License |
||||
WT00030660-2018 |
28
Mar 2018 |
31
Mar 2023 |
Valid |
- |
Notification of Construction Works under the Air Pollution Control (Construction
Dust) Regulation |
||||
429806 |
18 Jan 2018 |
End of Project |
Notified |
- |
Chemical Waste Producer Registration |
||||
WPN5213-225-B2526-01 |
14 March 2018 |
End of Project |
Valid |
- |
Billing Account for Disposal of Construction Waste |
||||
7029997 |
1 Feb 2018 |
End of Project |
Valid |
- |
Construction Noise
Permit |
||||
GW-RE0624-20 |
23 Jul 2020 |
22 Jan 2021 |
Valid until 22 Jan 2021 |
Construction
Noise Permit at Zone C |
GW-RE0087-21 |
29 Jan 2021 |
28 Apr 2021 |
Valid |
|
GW-RE0940-20 |
4 Nov 2020 |
4 May 2021 |
Superseded by GW-RE1120-20 |
Construction Noise
Permit at Zone A, B & MCHC. |
GW-RE1120-20 |
8 Jan 2021 |
7 Apr 2021 |
Valid |
Construction Noise
Permit at Zone A, B |
GW-RE1004-20 |
27 Nov 2020 |
26 May 2021 |
Valid |
Construction
Noise Permit at Multi-storey Car Park Building |
GW-RE0024-21 |
21 Jan 2021 |
20 Apr 2021 |
Valid |
Construction
Noise Permit at Zone D & G |
Marine Dumping Permit |
||||
EP/MD/21-071 |
22 Nov 2020 |
21 May 2021 |
Valid |
Type 1- Open Sea Disposal |
EP/MD/21-083 |
22 Dec 2020 |
21 Jan 2021 |
Valid until 21 Jan 2021 |
Type 1- Open Sea Disposal (Dedicated Site) and Type 2- Confined Marine
Disposal |
EP/MD/21-098 |
22 Jan 2021 |
21 Feb 2021 |
Valid |
2.1. Environmental permit (EP) conditions under the EIAO, submission status under the EP and implementation status of mitigation measures had been reviewed and implemented on schedule. The status of required submissions under the EP (EP-457/2013/C) and FEP (FEP-02/457/2013/C) as of the reporting period for the Project are summarised in Table 2.1
Table 2.1 Summary of
Status of Required Submission for EP-457/2013/C and
FEP-02/457/2013/C for the
Project
EP/FEP Condition (EP-457/2013/C) (FEP-02/457/2013/C) |
Submission |
Submission date |
Notification of Commencement Date of Construction
of the Project |
||
2 Dec 2020 |
||
14 Jan 2021 |
2.2. Details of the major construction activities reported by Main Contractor in this reporting period are shown in Table 2.2.
Table 2.2 Summary of the Construction Activities reported by Main Contractor during the Reporting Month. PENDING
Construction activities
undertaken |
Remarks on
progress |
·
Install 406mm pipe piles at YMTPS |
· 82% completion |
·
Construction of D-wall panels (31 panels) at Zone B |
· 90% completion |
·
Site formation,
predrilling, remedial works for land contamination, grout curtain wall &
guide wall & D-wall at Zone B |
· 23% completion |
·
Construction of Stage 3 D-wall panels, soil improvement works, sheet
piling at Zone C |
· 55% completion |
·
Demolition of YMTSCE building including substructure removal |
· Completed |
·
Demolition of Car Park
Building including Advance Works and Substructure Removal |
· 12% completion |
·
Guide
wall, D-wall and pipe piles at Zone D |
· 8% completion |
·
Predrilling,
pipe piles & TTA Stage 4 at Zone G1 (Stage 1) |
· 10% completion |
·
ELS, Excavation and
Construction of Pad Footing, Piers and Portal Frame for RGRF |
· 20% completion |
·
CLP Cable Diversion, demolition of subway/ backfill & predrilling
at Zone D |
· 20% completion |
2.3. The drawing showing the the project layout and the location of the monitoring station and environmental sensitive receivers are attached in Appendix A and Appendix K. Co-ordinates of the monitoring location and temporary alternative monitoring location are shown in Table 2.3 and Table 2.4 respectively:
Table 2.3 Summary for the location of the monitoring station
Monitoring Location |
Location ID |
Latitude |
Longitude |
Yau Ma Tei Catholic Primary School (Hoi Wang
Road) |
W-A1/ W-N1A |
||
Man Cheong Building |
W-A6 |
||
Hydan Place |
W-N18 |
||
Prosperous Garden Block 1 |
W-N25A |
||
The Coronation Tower 1 |
W-P11 |
Table 2.4 Summary for the location of the temporary alternative monitoring station
Monitoring Location |
Location ID |
Latitude |
Longitude |
Roadside infront of The Hong Kong Police
Force Yau Ma Tei Divisional Station |
W-P11-T |
22.310106 |
114.166211 |
3.
Monitoring Results
Air Quality
3.1.1. The impact monitoring had been carried out in accordance with section 5.8 of the approved EM&A Manual to determine the 1-hour and 24-hour total suspended particulates (TSP) levels at the monitoring locations in the reporting month.
3.1.2. The sampling frequency of at least once in every 6 days, shall be strictly observed at the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least 3 times in every 6 days should be undertaken when the highest dust impact occurs.
3.1.3. General meteorological conditions (wind speed, direction and precipitation) and notes regarding any significant adjacent dust producing sources had also been recorded throughout the impact monitoring period.
Noise
3.1.4. Construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30min) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays.
3.1.5. For all other time periods, Leq (5min) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria.
3.1.6. As supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.
Air
Quality
3.2.1. 1-hour TSP levels and 24-hour TSP had been measured with direct reading dust meter and High Volume Samplers respectively. It has been demonstrated its capability in achieving comparable results with high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50).
3.2.2. The 1-hour TSP meter was calibrated by the manufacturer prior to purchasing. Zero response of the instrument was checked before and after each monitoring event. Operation of the 1-hour TSP meter followed manufacturer’s Operation and Service Manual. The 24-hour TSP meter was calibrated against firmware 80570-8100-V1.0.4, annually. Operation of the 24-hour TSP meter followed manufacturer’s Operation and Service Manual. Valid calibration certificates of dust monitoring equipment are attached in Appendix H.
3.2.3. A summary of the equipment that was deployed for the 24- hour averaged monitoring is shown in Table 3.1. The TSP monitoring was conducted as per the schedule presented in Appendix G.
3.2.4. The equipment used for 1-hour TSP and 24-hour TSP measurement and calibration are summarised in Table 3.1
Table 3.1 Construction
Dust Monitoring Equipment
Monitoring
Parameter |
Monitoring
Equipment |
Serial Number |
Date of Calibration |
1-hour TSP |
LD-5R Digital Dust Indicator |
882106 |
22 Jul 2020 |
LD-5R Digital Dust Indicator |
851819 |
22 Jul 2020 |
|
24-hour TSP |
TE-5170X High Volume Sampler |
1049 |
2, 15 Jan 2021 |
TE-5170X High Volume Sampler |
1050 |
2, 15 Jan 2021 |
|
TE-5025A Calibration Kit |
3465 |
23 Sep 2020 |
Noise
3.2.5. Sound level meter in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications has been used for carrying out the noise monitoring. The sound level meter has been checked using an acoustic calibrator. The wind speed and other metrological data has been recorded from Hong Kong Observatory- King’s Park meteorological station, along with portable wind speed meter stand by as back up when the information are not available from HKO.
3.2.6. An acoustic calibrator and sound level meter using for the monitoring is within the valid period and were calibrated per year. Valid calibration certificate of noise monitoring equipment is attached in Appendix I.
3.2.7. The details of equipment using for monitoring are listed in Table 3.2, as below:
Table 3.2 Monitoring Equipment Used in Monitoring
Monitoring
Equipment |
Serial Number |
Date of
Calibration |
Nti XL2 Sound Level Meter |
A2A-13548-E0 |
12 Dec
2020 |
Pulsar
105 Acoustic Calibrator |
63705 |
6 Aug
2020 |
3.3. Monitoring Methodology and QA/QC results
Air Quality
3.3.1. The 1-hour TSP monitor, portable dust meters (Sibata Digital Dust Indicator Model LD-5R) was used for the impact monitoring. The 1-hour TSP meters provides a real time 1-hour TSP measurement based on 90o light scattering. Three 1-hour TSP level were logged per every six days.
3.3.2. The 24-hour TSP monitor, High Volume Samplers (Tisch TE-5170X High Volume Air Sampler) were used for the impact monitoring. The 24-hour TSP monitoring consists of the following:
u The HVS was set at the monitoring location, with
electricity supply connected and secured;
u HVS was calibrated before commencing the 1st
measurement;
u The filter paper was weight and provided by HOKLAS
lab (Acumen Laboratory and Testing Limited and ALS Technichem
(HK) Pty Ltd) before and after the sampling. Certificate of HOKLAS accredited
laboratory can be referred to Appendix J;
u The airflow over time during sampling process was
recorded by the HVS.
3.3.3. HVSs were free-standing with no obstruction. The following criteria were considered in the installation of the HVS:
u Appropriate support to secure the samples against
gusty wind needed to be provided the monitoring station;
u A minimum of 2m separation from walls, parapets and
penthouses was required for rooftop samplers;
u No furnace or incinerator flues was nearby;
u Airflow around the sampler was unrestricted; and
u Permission could be obtained to set up the samplers
and gain access to the monitoring station.
3.3.4. Preparation of Filter Papers
u Glass fiber filters were labelled and sufficient
filters that were clean and without pinholes were selected;
u All filters were equilibrated in the conditioning
environment for 24 hours before weighing. The conditioning environment
temperature was around 25℃ and not varied by more than ±3℃; the
relative humidity (RH)was 40%; and
u Acumen Laboratory and Testing Limited and ALS Technichem (HK) Pty Limited, as HOKLAS accredited
laboratory, implemented comprehensive quality assurance and quality control programmes on the filters.
u The power supply was checked to ensure that the HVS
was working properly;
u The filter holder and area surrounding the filter
were cleaned;
u The filter holder was removed by loosening the foul
bolts and a new filter, with stamped number upward, on a supporting screen was
aligned carefully;
u The filter was properly aligned on the screen so
that the gasket formed an airtight seal on the outer edges of the filter;
u The swing bolts were fastened to hold the filter
holder down to the frame. The pressure applied should be sufficient to avoid
air leakage at the edges;
u The shelter lid was closed and secured with an
aluminum strip;
u The HVS was warmed- up for about 5 minutes to
establish run- temperature conditions;
u A new flow rate record sheet was inserted into the
flow recorder;
u The flow rates of the HVS was
checked and adjusted to between 1.22-1.37m3min-1, which was within the range specified in the
EM&A Manual (i.e. 0.6- 1.7m3min-1);
u The programmable timer was set for a sampling
period of 24 hours, and the starting time, weather condition and filter number
were recorded;
u The initial elapsed time was recorded;
u At the end of sampling, the sampled filter was
removed carefully and folded in half so that only surfaces with collected
particulate matter were in contact;
u The filter paper was placed in a clean plastic
envelope and sealed; all monitoring information was recorded on a standard data
sheet and
u The filters were sent to (Acumen Laboratory and
Testing Ltd and ALS Technichem (HK) Pty Ltd) for
analysis.
3.3.6. Maintenance and Calibration
u The HVS and their accessories were maintained in a
good working condition. For example, motor brushes were replaced routinely and electrical wiring was checked to ensure a
continuous power supply; and
u The flow rate of each HVS with mass flow controller
was calibrated using an orifice calibrator, Initial calibrations of the dust
monitoring equipment were conducted upon installation and prior to
commissioning. Five- point calibration was carried out for HVS using TE-5025 Calibration
Kit. HVS is calibrated bimonthly. The calibration records for the HVS is given in Appendix H.
u The wind speed has been recorded from Hong Kong
Observatory- King’s Park meteorological station, along with portable wind speed
meter stand by as back up when the information are not
available from HKO.
Noise
3.3.8. All noise measurements by the meter were set to FAST response and on the A-weighted equivalent continuous sound pressure level (Leq) in decibels dB(A). LAeq(30min) was used as the monitoring metric for the time period between 0700 –1900 hours on normal weekdays. The measured noise levels were logged every 5 minutes throughout the monitoring period.
3.3.9. Prior to the noise measurement, the accuracy of the sound level meter was checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Checking was conducted before and after the monitoring. The calibration level before and after the noise measurement is agreed to within 1.0 dB(A).
3.3.10. Noise measurements should not be made in presence of fog, rain, wind with a steady speed exceeding 5 ms-1 or wind with gusts exceeding 10 ms-1. The wind speed was checked with a portable wind speed meter capable of measuring with speeds in ms-1.
Air Quality
3.4.1. During the site visit, both of the original proposed dust monitoring locations were rejected due to the condition at The Coronation was not favorable for monitoring and the access was declined by the management office of Hong Kong Community College (HKCC) of PolyU. Two alternative air monitoring stations Yau Ma Tel Catholic Primary School (Hoi Wang Road) and Man Cheong Building had been proposed by ET and approved by IEC. 2 designated air monitoring locations were identified and agreed with IEC and EPD. Details of air monitoring stations are described in Table 3.3. The location plan of air quality monitoring stations is shown in Appendix K.
Table 3.3 Location of the Dust Monitoring Stations
Air Quality
Monitoring Station |
Dust Monitoring |
W-A1 |
Yau Ma Tei Catholic Primary School (Hoi Wang
Road) |
W-A6 |
Man Cheong Building |
Noise
3.4.2.
During the site visit, one of
the original proposed noise monitoring locations Tak Cheong Building was
rejected by the president of the owner’s corporation. Alternative noise
monitoring station Hydan place had been proposed by ET and approved by
IEC. 4 noise sensitive receivers designated noise monitoring locations were
identified and agreed with IEC and EPD. The designated monitoring stations are identified and access was granted by the premises. The
details of noise monitoring stations are described in Table 3.4 and the
location plan of noise monitoring station is shown in Appendix K.
Table 3.4 Noise Monitoring
Stations
Noise Monitoring Station |
Identified
Noise Monitoring
Station |
Type of
Measurement |
W-N1A |
Yau Ma Tei Catholic Primary School (Hoi Wang
Road) |
Façade |
W-N18 |
Hydan Place |
Façade |
W-N25A |
Prosperous Garden Block 1 |
Façade |
W-P11 |
The Coronation Tower 1 |
Façade |
3.4.3. Noise monitoring at the Coronation Tower 1 (W-P11) was temporarily suspended on 27 January 2021 due to a case of novel coronavirus infection at the Coronation Circle on 17 January 2021. Temporary alternative noise monitoring location, W-P11-T was used to conduct noise monitoring on 27 January 2021. Details of temporary alternative monitoring location are presented in Temporary Alternative Proposal for Monitoring Station as proposed by ET and agreed by IEC dated 27 March 2020. The details of noise monitoring station are described in Table 3.5 and the location plan of noise monitoring station is shown in Appendix K.
Table 3.5 Temporary Alternative Noise Monitoring
Stations
Temporary Alternative Noise Monitoring Station |
Identified Noise Monitoring Station |
Type of Measurement |
W-P11-T |
Roadside infront of The
Hong Kong Police Force Yau Ma Tei Divisional
Station |
Free-field |
3.5. Monitoring date, time, frequency and duration
3.5.1. A summary of impact monitoring duration, sampling parameter and frequency is presented in Table 3.6.
Table 3.6: Summary of Impact Monitoring
Programme
Impact Monitoring |
Duration |
Sampling Parameter |
Frequency |
Dust |
1-hour
continuous measurement |
1-hour TSP |
3 times per six days |
Dust |
24-hour
continuous sampling |
24-hour TSP |
Once per six days |
Noise |
30-minute
continuous measurement |
Leq 30 min, L10 and L90
as reference. |
Once per week (0700 – 1900) |
Air Quality
3.6.1. According to our field observations, the major dust source identified at the designated air quality monitoring stations in the reporting month are summarised in Table 3.7
Table 3.7 Observation at Dust Monitoring Stations
Monitoring Station |
Major Dust Source |
W-A1 |
Nearby traffic |
W-A6 |
Nearby traffic |
3.6.2. Air quality impact monitoring for the reporting month was carried out on 4, 9, 15, 21, 27 January 2021 at W-A1 and on 4, 9, 15, 21 January 2021 at W-A6.
3.6.3. TSP monitoring at Man Cheong Building (W-A6) was temporarily suspended on 27 January 2021 as this station was located inside the specified areas.
3.6.4. The results for 1-hour TSP and 24-hour TSP are summarized in Table 3.8 and Table 3.9. The measurement data and details of influencing factors such as weather conditions and site observation are presented in Appendix L.
Table
3.8 Summary of 1-hour TSP Monitoring Results
Monitoring Location |
Range(μg/m3) |
Action Level(μg/m3) |
Limit Level(μg/m3) |
W-A1 |
37-63 |
319 |
500 |
W-A6 |
41-63 |
306 |
500 |
Table
3.9 Summary of 24-hour TSP Monitoring Results
Monitoring Location |
Range(μg/m3) |
Action Level(μg/m3) |
Limit Level(μg/m3) |
W-A1 |
51-113 |
167 |
260 |
W-A6 |
55-82 |
166 |
260 |
Noise
3.6.5.
According to our field
observations, the major noise source identified at the designated noise
monitoring station in the reporting month are summarised in Table 3.10:
Table 3.10 Observation at Noise Monitoring
Stations
Monitoring Station |
Major Noise Source |
W-N1A |
Nearby traffic |
W-N18 |
Nearby traffic |
W-N25A |
Nearby traffic |
W-P11 |
Nearby traffic |
W-P11-T |
Nearby traffic |
3.6.6.
The construction noise impact monitoring
for the reporting month was carried out on 4, 9, 15, 21, 27 January 2021. The measurement
data are shown in Appendix M and summarized in Tables 3.11.
Table
3.11 Summary of Noise Monitoring Results
Time
Period |
Monitoring location |
Parameter |
Range,
dB(A) |
|
|
||
Leq |
L10 |
L90 |
Action
Level |
Limit
Level# |
|||
Normal
working hour from 0700-1900 |
W-N1A |
Leq 30min |
59.5-63.1 |
60.8-69.4 |
56.7-57.9 |
When one documented complaint is received |
70dB(A) or 65 dB(A) during examination |
W-N18 |
65.2-69.7 |
67.3-72.5 |
62.5-67.4 |
75dB(A)# |
|||
W-N25A |
64.7-70.2 |
68.5-72.0 |
57.4-68.0 |
||||
W-P11^ |
66.2-69.9 |
67.8-72.3 |
64.0-65.5 |
||||
W-P11-T^ |
71.0 |
71.8 |
69.7 |
Remarks: |
1. # If works are to
be carried out during restricted hours, the conditions stipulated in the
construction noise permit by the Noise Control Authority have to be followed. 2. No examination
was held at W-N1A so limit level for all monitoring days were 70 dB(A). 3. ^Noise monitoring
at the Coronation Tower 1 (W-P11) was temporarily suspended on 27 January
2021 due to a case of novel coronavirus infection at the Coronation Circle on
17 January 2021. Temporary alternative noise monitoring location, W-P11-T was
used to conduct noise monitoring on 27 January 2021. Free field correction: Leq30min dB(A) +3 dB(A)is
applied for W-P11-T. |
3.6.7.
The waste generated from this
Project includes inert C&D materials, and non-inert C&D materials.
Non-inert C&D materials are made up of general refuse, vegetative wastes
and recyclable wastes such as plastics and paper/cardboard packaging waste.
Steel materials generated from the project are also grouped into non-inert
C&D materials as the materials were not disposed of with other inert
C&D materials. With reference to relevant handling records and trip tickets
of this Project, the quantities of different types of waste generated in the
reporting month are summarised in Table 3.12. Details of cumulative waste management data are presented as a waste flow table in Appendix N.
Table 3.12 Quantities of waste generated from
the Project
Reporting period |
Quantity |
|||||
Inert C&D Materials (in ‘tonnes) |
Chemical Waste (in‘000 Kg) |
Non-inert C&D Materials |
||||
Others, e.g. General Refuse disposed at Landfill (in ‘tonnes) |
Recycled materials |
|||||
Paper/card board (in ‘000
Kg) |
Plastics (in ‘000
Kg) |
Metals (in ‘000 Kg ) |
||||
Jan-2021 |
9118.8 |
20.7 |
89.3 |
0.0 |
0.0 |
0.0 |
4.
Summary of Complaints, Notification of Summons and
Prosecutions
4.1. The Environmental Complaint Handling Procedure is shown in below Table 4.1:
Table
4.1 Environmental Complaint Handling Procedure
Complaint Received via Project Hotline |
Complaint Received via 1823 or from other government departments |
|||||
|
|
|
|
|||
Contractor notify ER, ET and IEC |
ER notify Contractor, ET and IEC |
|||||
|
|
|
|
|||
Contractor log complaint and date of receipt onto the complaint database. Contractor, ER and ET to conduct investigation of complaint |
||||||
|
|
|
|
|||
If complaint is considered not valid |
If complaint is found valid |
|||||
|
|
|
|
|||
ET or ER to reply the complainant if necessary |
Contractor to identify and implement remedial measures in consultation with the IEC, ET and ER. |
|||||
|
|
|
|
|||
|
|
The ER, ET and IEC to review the effectiveness of the Contractor's remedial measures and the updated situation; ET to undertake additional monitoring and audit to verify the situation if necessary, and oversee that circumstances leading to the complaint do not recur. ER to conduct further inspection as necessary. |
||||
|
|
|
|
|||
If the complaint is referred by the EPD, the Contractor to prepare interim report on the status of the complaint investigation and follow-up actions stipulated above, including the details of the remedial measures and additional monitoring identified or already taken, for submission to EPD within the time frame assigned by the EPD |
||||||
|
|
|
||||
The ET to record the details of the complaint, results of
the investigation, subsequent actions taken to address the complaint and
updated situation including the effectiveness of the remedial measures,
supported by regular and additional monitoring results in the monthly
EM&A reports |
||||||
4.2.
Should non-compliance of the criteria occur,
action in accordance with the Action Plan in Appendix D and Appendix E shall be
carried out.
4.3.
No exceedance of Action Level and Limit Levels
of 24-hour TSP and 1-hour TSP and construction noise were recorded during the
reporting month.
4.4.
One Action Level of construction noise was triggered during
the reporting period as there was one documented complaint received on 28
January 2021 related to construction noise at Zone D2 and D3. No exceedance of
Limit Level of construction noise was recorded in the reporting month. No
exceedance of the Action Level and Limit Levels of 24-hour TSP and 1-hour TSP was
recorded during the reporting month.
4.5.
One noise-related complaint was received in
the reporting month on 28 January 2021. After investigation with Contractor,
precautionary measures had been proposed to the Contractor by ET. The interim
report for the complaint is shown in Appendix Q.
4.6.
No non-compliance was received in the
reporting month.
4.7. No notification of summons and prosecution was received in the reporting period.
4.8. Statistics on complaints, notifications of summons and successful prosecutions are summarized in Appendix O.
5.1. Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract. In the reporting period, four (4) site inspections were carried out on 7, 14, 21, 28 January 2021, along with bi-weekly inspection of the implementation of landscape and visual mitigation measures conducted on 14, 28 January 2021.
5.2. One joint site inspection with IEC also undertaken on 14 January 2021. Minor deficiencies were observed during weekly site inspection. Key observations during the site inspections are summarized in Table 5.1.
Table 5.1 Site
Observations
Date |
Environmental
Observations |
Follow-up Status |
7 January 2021 |
1. NRMM label was missing for an excavator
in Zone B2. |
1.
NRMM label was posted for the excavator in Zone B2. |
14 January 2021 |
1. Site runoff was observed outside site
boundary in Zone C. 2. Drip tray was missing for chemical
containers in Zone D2. 3. Stockpile of cement bags was not covered
completely with impervious sheeting in Zone D3. 4. Colour of NRMM label for an air compressor was
faded in Zone D3. |
1.
Site boundary was kept clear in Zone C. 2.
Chemical containers were placed on drip tray in Zone D2. 3.
Stockpile of cement bags was covered completely with
impervious sheeting in Zone D3. 4.
Coloured NRMM label was posted for
the air compressor in Zone D3. |
21 January 2021 |
1. NRMM labels for an excavator in Zone B
and boring machine and air compressor in Zone B2 had to be maintained. 2. Gully was not properly covered with
geotextile and sandbags to prevent site runoff from going into permanent
drainage channel in Zone C. |
1.
Excavator was moved away from Zone B. NRMM labels were
posted for the boring machine and air compressor in Zone B2. 2.
Gully was properly protected to prevent site runoff from
going into permanent drainage channel in Zone C. |
28 January 2021 |
1. Drip tray had to be provided for chemical
containers in Zone B2 and D3. 2. Colour of NRMM label for a generator in Zone C
was faded. |
1.
Chemical containers were placed on drip tray in Zone B2 and
D3. 2.
Coloured NRMM label was posted
for the generator in Zone C. |
5.3. The Contractor had rectified all observation identified during
environmental site inspection in the reporting period.
5.4. According to the EIA Study Report, Environmental Permit, contract documents and EM&A Manual, the mitigation measures detailed in the documents are implemented as much as practical during the reporting period. An updated Implementation Status of Environmental Mitigation Measures (EMIS) is provided in Appendix F.
6.
Future Key Issues
6.1. The construction activities provided by Main Contractor in the next reporting month are:
·
Removal
of remaining waling and struts at Zone A
·
Continue
for D-wall construction at Zone B
·
Predrilling
works, utilities diversion works, site formation works, guide wall, pre-boring
works and D-wall construction at Zone B.
·
Phase 3
Works (Construction of New Refuse Collection Area) for Methadone Clinic
·
Continue for D-wall construction, Underpinning
Works for existing Piers, CLP cable diversion at Zone C
·
Works
for GRF at HKAA area: carry out ELS part B and pad footing construction
and pier construction.
·
Continue
for advance works (covered walkway erection, liaison/PR works, removal
of asbestos and furniture) for demolition works at
carpark building
·
Continue
for outstanding works for Phase 2 at Temporary Public Library Cum Jade Hawker
Bazaar Building (TPLCJHB) and complete decantation of existing JHB
·
CLP
cable diversion, predrilling works, demolition of subway, backfilling of subway
at removal of trees (pending tree felling permit), site formation works of zone
3 for noise enclosure works
·
Implement
TTA along Ferry Street to commence predrilling works at west side of Zone 3
Noise Enclosure
·
Continue
pre-coring works, pipe piling works and
commence D-wall construction at Zone D
·
Commence Pipe
Piles installation at Zone G1 (Stage 1)
·
Implement TTA
Stage 3 to facilitate works along Kansu Street
·
Monitoring
of instrumentation for all areas
6.2. Potential environmental impacts arising from the above construction activities are mainly associated with dust, construction noise and waste management.
6.3. The tentative schedule of regular construction noise monitoring, 1-hour TSP and 24-hour TSP monitoring in the next reporting period is presented in Appendix P.
6.4. The construction programme for the Project for the next reporting month is presented in Appendix B.
7.
Conclusion and Recommendations
7.1. This 34th monthly EM&A Report presents the EM&A works undertaken during the period from 1 January 2021 to 31 January 2021 in accordance with the EM&A Manual and the requirement under EP- 457/2013/C and FEP-02/457/2013/C.
7.2.
Air quality (including 1-hour
TSP and 24-hour TSP) and noise impact monitoring were carried out in the
reporting period. No exceedance of the Action Level and Limit
Level was recorded for construction noise and air quality impact monitoring
during the reporting month.
7.3.
Noise monitoring at the Coronation Tower 1
(W-P11) was temporarily suspended on 27 January 2021 due to a case of novel
coronavirus infection at the Coronation Circle on 17 January 2021. Temporary
alternative noise monitoring location, W-P11-T was used to conduct noise
monitoring on 27 January 2021. Details of temporary alternative monitoring
location are presented in Temporary Alternative Proposal for Monitoring Station
as proposed by ET and agreed by IEC dated 27 March 2020. On the other hand, the
Government had expanded the specified areas for
compulsory COVID-19 testing on 26 January 2021. The specified areas were
recognized as high risk areas. TSP monitoring at Man
Cheong Building (W-A6), noise monitoring at Hydan
Place (W-N18), and noise monitoring at Prosperous Garden Block 1
(W-N25A/W-N25A-T) were temporarily suspended from 27 January 2021 to 9 February
2021 as these stations were located inside or in proximity to the specified
areas.
7.4. Weekly environmental site inspections were conducted during the reporting period. Joint site inspection with IEC were carried out on 14 January 2021. Minor deficiency was observed during site inspection and was rectified within the specified deadlines. The environmental performance of the Project was therefore considered satisfactory.
7.5.
One Action Level of construction noise was triggered during
the reporting period as there was one documented complaint received on 28
January 2021 related to construction noise at Zone D2 and D3. No exceedance of
Limit Level of construction noise was recorded in the reporting month. No
exceedance of the Action Level and Limit Levels of 24-hour TSP and 1-hour TSP was
recorded during the reporting month.
7.6.
One noise-related complaint was received in
the reporting month on 28 January 2021. After investigation with Contractor,
precautionary measures had been proposed to the Contractor by ET. The interim
report for the complaint is shown in Appendix Q.
7.7.
No non-compliance was reported in the
reporting month.
7.8. No notification of summons or prosecution was received in the reporting month.
7.9. The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.
Appendix A
Alignment and Works Area For the Contract No. HY/2014/08
Appendix B
Construction
Programme
Appendix C
Project Organization Chart
Project O-Chart
Appendix D
Dust Event-Action Plan (EAP)
EVENT |
ACTION |
|||
ET |
IEC |
ER |
CONTRACTOR |
|
ACTION LEVEL |
||||
1.Exceedance for one sample |
1. Identify source, investigate
the causes of exceedance and propose remedial measures; 2. Inform IEC and ER; 3. Repeat measurement to confirm finding; 4. Increase monitoring frequency
to daily. |
1. Check monitoring data submitted
by ET; 2. Check Contractor’s working
method. |
1. Notify Contractor. |
1. Rectify any unacceptable practice; 2. Amend working methods if
appropriate. |
2.Exceedance for two or more
consecutive samples |
1. Identify source; 2. Inform IEC and ER; 3. Advise the ER on the
effectiveness of the proposed remedial measures; 4. Repeat measurements to confirm findings; 5. Increase monitoring frequency
to daily; 6. Discuss with IEC and Contractor
on remedial actions required; 7. If exceedance continues,
arrange meeting with IEC and ER; 8. If exceedance stops, cease
additional monitoring. |
1. Check monitoring data submitted
by ET; 2. Check Contractor’s working method; 3. Discuss with ET and Contractor
on possible remedial measures; 4. Advise the ET on the
effectiveness of the proposed remedial measures; 5. Supervise Implementation of
remedial measures. |
1. Confirm receipt of notification
of failure in writing; 2. Notify Contractor; 3. Ensure remedial measures
properly implemented. |
1. Submit proposals for remedial
to ER within 3 working days of notification; 2. Implement the agreed proposals; 3. Amend proposal if appropriate. |
LIMIT LEVEL |
||||
1.Exceedance for one sample |
1. Identify source, investigate
the causes of exceedance and propose remedial measures; 2. Inform ER, Contractor and EPD; 3. Repeat measurement to confirm finding; 4. Increase monitoring frequency
to daily; 5. Assess effectiveness of
Contractor’s remedial actions and keep IEC, EPD and ER informed of the
results. |
1. Check monitoring data submitted
by ET; 2. Check Contractor’s working method; 3. Discuss with ET and Contractor
on possible remedial measures; 4. Advise the ER on the
effectiveness of the proposed remedial measures; 5. Supervise implementation of
remedial measures. |
1. Confirm receipt of notification
of failure in writing; 2. Notify Contractor; 3. Ensure remedial measures
properly implemented. |
1. Take immediate action to avoid
further exceedance; 2. Submit proposals for remedial
actions to IEC within 3 working days of notification; Implement the agreed proposals; 4. Amend proposal if appropriate. |
2.Exceedance for two or more
consecutive samples |
1. Notify IEC, ER, Contractor and EPD; 2. Identify source; 3. Repeat measurement to confirm findings; 4. Increase monitoring frequency
to daily; 5. Carry out analysis of
Contractor’s working procedures to determine possible mitigation to be implemented; 6. Arrange meeting with IEC and ER
to discuss the remedial actions to be taken; 7. Assess effectiveness of
Contractor’s remedial actions and keep IEC, EPD and ER informed of the results; 8. If exceedance stops, cease
additional monitoring. |
1. Discuss amongst ER, ET, and
Contractor on the potential remedial actions; 2. Review Contractor’s remedial
actions whenever necessary to assure their effectiveness and advise the ER accordingly; 3. Supervise the implementation of
remedial measures. |
1. Confirm receipt of notification
of failure in writing; 2. Notify Contractor; 3. In consultation with the IEC,
agree with the Contractor on the remedial measures to be implemented; 4. Ensure remedial measures
properly implemented; 5. If exceedance continues,
consider what portion of the work is responsible and instruct the Contractor
to stop that portion of work until the exceedance is abated. |
1. Take immediate action to avoid
further exceedance; 2. Submit proposals for remedial
actions to IEC within 3 working days of notification; 3. Implement the agreed proposals; 4. Resubmit proposals if problem
still not under control; 5. Stop the relevant portion of
works as determined by the ER until the exceedance is abated. |
Note:
ET – Environmental Team ER – Engineer’s Representative
IEC – Independent Environmental Checker
Appendix E
Noise Event-Action Plan
(EAP)
EVENT |
ACTION |
|||
ET |
IEC |
ER |
CONTRACTOR |
|
Action Level |
1. Identify source, investigate the causes of
exceedance and propose remedial measures; 2. Notify IEC and Contractor; 3. Report the results of investigation to the IEC,
ER and Contractor; 4. Discuss with the Contractor and formulate
remedial measures; 5. Increase monitoring frequency to check mitigation
effectiveness. |
1.Review the analysed results submitted by the ET; 2. Review the proposed remedial measures by the
Contractor and advise the ER accordingly; 3. Supervise the implementation of remedial
measures. |
1. Confirm
receipt of notification of failure in writing; 2. Notify Contractor; 3. Require
Contractor to propose remedial measures for the analysed noise problem; 4. Ensure
remedial measures are properly implemented |
1. Submit noise mitigation proposals to IEC; 2. Implement noise mitigation proposals. |
Limit Level |
1. Identify source; 2. Inform IEC, ER, EPD and Contractor; 3. Repeat measurements to confirm findings; 4. Increase monitoring frequency; 5. Carry out analysis of Contractor’s working
procedures to determine possible mitigation to be implemented; 6. Inform IEC, ER and EPD the causes and actions
taken for the exceedances; 7. Assess effectiveness of Contractor’s remedial actions
and keep IEC, EPD and ER informed of the results; 8. If exceedance stops, cease additional monitoring. |
1. Discuss amongst ER, ET, and Contractor on the
potential remedial actions; 2. Review Contractors remedial actions whenever
necessary to assure their effectiveness and advise the ER accordingly; 3. Supervise the implementation of remedial
measures. |
1.Confirm receipt of notification of failure in writing; 2. Notify Contractor; 3. Require Contractor to propose remedial measures
for the analysed noise problem; 4. Ensure remedial measures properly implemented; 5. If exceedance continues, consider what portion of
the work is responsible and instruct the Contractor to stop that portion of
work until the exceedance is abated. |
1. Take immediate action to avoid
further exceedance; 2. Submit proposals for remedial
actions to IEC
within 3 working days of notification; 3. Implement the agreed proposals; 4. Resubmit proposals if problem
still not under control; 5. Stop the relevant portion of
works as determined by the ER until the exceedance is abated. |
Note:
ET – Environmental Team
IEC – Independent Environmental Checker
ER – Engineer’s Representative
Appendix F
Environmental Mitigation
Implementation Schedule (EMIS)
Environmental Mitigation Implementation Schedule – Contract No. HY/2014/08 (Yau Ma Tei East) |
|
||||||||
|
|||||||||
EIA Ref. |
EM&A Log Ref. |
Recommended Mitigation Measures |
Objectives of the Recommended
Measures & Main Concerns to address |
Implementation Agent |
Location / Timing |
Implementation Stage |
Requirements and/ or standards to be
achieved |
Implementation Status |
|
Construction Dust Impact |
|||||||||
S4.3.10 |
D1 |
The contractor
shall follow the procedures and requirements given in the Air Pollution
Control (Construction Dust) Regulation |
Minimize dust impact
at the nearby sensitive receivers |
Contractor |
All construction sites |
Construction stage |
·
APCO ·
To
control the dust impact To meet HKAQO and TM-EIA
criteria |
·
Implemented,
deficiency rectified after observation. |
|
S4.3.10 |
D2 |
·
Mitigation
measures in form of regular watering under a good site practice should be
adopted. Watering once per hour on
exposed worksites and haul road should be conducted to achieve dust removal
efficiencies of 91.7%. While the above
watering frequencies are to be followed, the extent of watering may vary
depending on actual site conditions but should be sufficient to maintain an
equivalent intensity of no less than 1.3 L/m2 to achieve the dust
removal efficiency. |
Minimize dust
impact at the nearby sensitive receivers |
Contractor |
All construction sites |
Construction stage |
·
APCO ·
To
control the dust impact To meet HKAQO and TM-EIA
criteria |
·
Implemented |
|
S4.3.10 |
D3 |
·
Proper
watering at exposed spoil should be undertaken throughout the construction
phase; ·
Any
excavated or stockpile of dusty material should be covered entirely by
impervious sheeting or sprayed with water to maintain the entire surface wet
and then removed or backfilled or reinstated where practicable within 24
hours of the excavation or unloading; ·
Any
dusty materials remaining after a stockpile is removed should be wetted with
water and cleared from the surface of roads; ·
A
stockpile of dusty material should not be extended beyond the pedestrian
barriers, fencing or traffic cones; ·
The
load of dusty materials on a vehicle leaving a construction site should be
covered entirely by impervious sheeting to ensure that the dusty materials do
not leak from the vehicle. ·
Where
practicable, vehicle washing facilities with high pressure water jet should
be provided at every discernible or designated vehicle exit point. The area where vehicle washing takes place
and the road section between the washing facilities and the exit point should
be paved with concrete, bituminous materials or hardcores; ·
When
there are open excavation and reinstatement works, hoarding of not less than
2.4m high should be provided and properly maintained as far as practicable
along the site boundary with provision for public crossing. Good site practice shall also be adopted by
the Contractor to ensure the conditions of the hoardings are properly
maintained throughout the construction period; ·
The
portion of any road leading only to construction site that is within 30m of a
vehicle entrance or exit should be kept clear of dusty materials; ·
Surfaces
where any pneumatic or power-driven drilling, cutting, polishing or other
mechanical breaking operation takes place should be sprayed with water or a
dust suppression chemical continuously; ·
Any
area that involves demolition activities should be sprayed with water or a
dust suppression chemical immediately prior to, during and immediately after
the activities so as to maintain the entire surface wet;
·
Any
skip hoist for material transport should be totally enclosed by impervious sheeting; ·
Every
stock of more than 20 bags of cement or dry-pulverised
fuel ash (PFA) should be covered entirely by impervious sheeting or placed in
an area sheltered on the top and the 3 sides; ·
Loading,
unloading, transfer, handling or storage of bulk cement or dry PFA should be
carried out in a totally enclosed system or facility, and any vent or exhaust
should be fitted with an effective fabric filter or equivalent air pollution
control system ·
Exposed
earth should be properly treated by compaction, turfing, hydroseeding,
vegetation planting or sealing with latex, vinyl, bitumen, shotcrete or other
suitable surface stabilizer within six months after the last construction
activity on the construction site or part of the construction site where the
exposed earth lies. |
Minimize dust
impact at the nearby sensitive receivers |
Contractor |
All construction sites |
Construction stage |
·
APCO ·
To
control the dust impact To meet HKAQO and TM-EIA
criteria |
·
Implemented,
deficiency rectified after observation. |
|
S4.3.10 |
D6 |
Implement regular dust monitoring
under EM&A programme during the construction
stage. |
Monitoring of dust impact |
Contractor |
Selected rep. dust monitoring station |
Construction stage |
·
TM-EIA |
·
Implemented |
|
Construction Noise (Airborne) |
|||||||||
S5.4.1 |
N1 |
Implement the following good site practices: ·
Only
well-maintained plant should be operated on-site and
plant should be serviced regularly during the construction programme; ·
Machines
and plant (such as trucks, cranes) that may be in intermittent use should be
shut down between work periods or should be throttled down to a minimum; ·
Plant
known to emit noise strongly in one direction, where possible, be orientated
so that the noise is directed away from nearby NSRs; ·
Silencers
or mufflers on construction equipment should be properly fitted and
maintained during the construction works; ·
Mobile
plant should be sited as far away from NSRs as possible and practicable; ·
Material
stockpiles, mobile container site office and other structures should be
effectively utilized, where practicable, to screen noise from on-site
construction activities. |
Control
construction airborne noise |
Contractor |
All construction sites |
Construction stage |
·
Annex
5, TM-EIAO |
·
Implemented |
|
S5.4.1 |
N2 |
Install temporary hoarding located on
the site boundaries between noisy construction activities and NSRs. The conditions of hoardings shall be
properly maintained throughout the construction period. |
Reduce the
construction noise levels at low-level zone of NSRs through partial screening |
Contractor |
All construction sites |
Construction stage |
·
Annex
5, TM-EIAO |
·
Implemented |
|
S5.4.1 |
N3 |
Install movable noise barriers
(typical design is wooden framed barrier with a small-cantilevered on a skid
footing with 25mm thick internal sound absorptive lining), acoustic mat or
full enclosure, screen the noisy plants including air compressors, generators
and handheld breakers, etc. |
Sreen the noisy plant items to be used at all
construction sites |
Contractor |
All construction sites where practicable |
Construction stage |
·
Annex
5, TM-EIAO |
·
Implemented |
|
S5.4.1 |
N4 |
Use ‘Quiet plant’ |
Reduce the noise
levels of plant items |
Contractor |
All construction sites where practicable |
Construction stage |
·
Annex
5, TM-EIAO |
·
Implemented |
|
S5.4.1 |
N5 |
Loading/ unloading activities should
be carried out inside the full enclosure of mucking out points. |
Reduce the noise
levels of loading/ unloading activities |
Contractor |
Mucking out locations |
Construction stage |
·
Annex
5, TM-EIAO |
·
Implemented |
|
S5.4.1 |
N6 |
Sequencing operation of construction
plants where practicable. |
Operate
sequentially within the same work site to reduce the construction airborne
noise |
Contractor |
All construction sites where practicable |
Construction stage |
·
Annex
5, TM-EIAO |
·
Implemented |
|
S5.4.1 |
N7 |
Implement a noise monitoring programme under EM&A programme.
|
Monitor the
construction noise levels at the selected representative locations |
Contractor |
Selected rep. noise monitoring station |
Construction stage |
·
TM-EIAO |
·
Implemented |
|
Water Quality (Construction Phase) |
|||||||||
S6.9.1.1 |
W1 |
In accordance with
the Practice Note for Professional Persons on Construction Site Drainage,
Environmental Protection Department, 1994 (ProPECC
PN1/94), construction phase mitigation measures shall include the following: Construction
Runoff ·
At
the start of site establishment, perimeter cut-off drains to direct off-site
water around the site should be constructed with internal drainage works and
erosion and sedimentation control facilities implemented. Channels (both temporary and permanent
drainage pipes and culverts), earth bunds or sand bag
barriers should be provided on site to direct stormwater to silt removal
facilities. The design of the
temporary on-site drainage system will be undertaken by the contractor prior
to the commencement of construction; ·
The
dikes or embankments for flood protection should be implemented around the
boundaries of earthwork areas.
Temporary ditches should be provided to facilitate the runoff
discharge into an appropriate watercourse, through a silt/ sediment
trap. The sediment/ silt traps should
be incorporated in the permanent drainage channels to enhance deposition rates; ·
The
design of efficient silt removal facilities should be based on the guidelines
in Appendix A1 of ProPECC PN 1/94, which states
that the retention time for silt/ sand traps should be 5 minutes under
maximum flow conditions. Sizes may
vary depending upon the flow rate, but for a flow rate of 0.1 m3/s a
sedimentation basin of 30 m3 would be required and for a flow rate of 0.5 m3/s
the basin would be 150 m3. The
detailed design of the sand/ silt traps shall be undertaken by the contractor
prior to the commencement of construction; ·
All
exposed earth areas should be completed and vegetated as soon as possible
after earthworks have been completed, or alternatively, within 14 days of the
cessation of earthworks where practicable.
Exposed slope surfaces should be covered by tarpaulin or other means; ·
The
overall slope of the site should be kept to a minimum to reduce the erosive
potential of surface water flows, and all traffic areas and access roads
protected by coarse stone ballast. An
additional advantage accruing from the use of crushed stone is the positive
traction gained during prolonged periods of inclement weather and the
reduction of surface sheet flows; ·
All
drainage facilities and erosion and sediment control structures should be
regularly inspected and maintained to ensure proper and efficient operation
at all times and particularly following rainstorms. Deposited silt and grit should be removed
regularly and disposed of by spreading evenly over stable, vegetated areas; ·
Measures
should be taken to minimize the ingress of site drainage into
excavations. If the excavation of
trenches in wet periods is necessary, they should be dug and backfilled in
short sections wherever practicable.
Water pumped out from trenches or foundation excavations should be discharged
into storm drains via silt removal facilities; ·
Open
stockpiles of construction materials (for example, aggregates, sand and fill
material) of more than 50m3 should be covered with tarpaulin or similar
fabric during rainstorms. Measures
should be taken to prevent the washing away of construction materials, soil,
silt or debris into any drainage system; ·
Manholes
should always be adequately covered and temporarily sealed so as to prevent
silt, construction materials or debris being washed into the drainage system
and storm runoff being directed into foul sewers; ·
Precautions
be taken at any time of year when rainstorms are likely, actions to be taken
when a rainstorm is imminent or forecasted, and actions to be taken during or
after rainstorms are summarized in Appendix A2 of ProPECC
PN 1/94. Particular attention should
be paid to the control of silty surface runoff during storm events,
especially for areas located near steep slopes; ·
All
vehicles and plant should be cleaned before leaving a construction site to
ensure no earth, mud, debris and the like is deposited by them on roads. An adequately designed and site wheel
washing facilities should be provided at every construction site exit where
practicable. Wash-water should have
sand and silt settled out and removed at least on a weekly basis to ensure
the continued efficiency of the process.
The section of access road leading to, and exiting from, the wheel
wash bay to the public road should be paved with sufficient backfall toward
the wheel wash bay to prevent vehicle tracking of soil and silty water to
public roads and drains; ·
Oil
interceptors should be provided in the drainage system downstream of any oil/
fuel pollution sources. The oil
interceptors should be emptied and cleaned regularly to prevent the release
of oil and grease into the storm water drainage system after accidental
spillage. A bypass should be provided
for the oil interceptors to prevent flushing during heavy rain; ·
Construction
solid waste, debris and rubbish on site should be collected, handled and
disposed of properly to avoid water quality impacts; ·
All
fuel tanks and storage areas should be provided with locks and sited on
sealed areas, within bunds of a capacity equal to 110% of the storage
capacity of the largest tank to prevent spilled fuel oils from reaching water
sensitive receivers nearby; ·
Adopt
best management practices; ·
All
earth works should be conducted sequentially to limit the amount of
construction runoff generated from exposed areas during the wet season (April
to September) as far as practicable. |
To minimize water
quality impact from the construction site runoff and general construction
activities |
Contractor |
All construction sites where practicable |
Construction stage |
·
Water
Pollution Control Ordinance ·
ProPECC PN 1/94 ·
TM-EIAO ·
TM-DSS |
·
Implemented,
deficiency rectified after observation. |
|
S6.9.1.2 |
W2 |
Tunneling
Works and Underground Works ·
Cut-&-cover
tunneling work should be conducted sequentially to limit the amount of construction runoff generated
from exposed areas during the wet season (April to September)
as far as practicable. ·
Uncontaminated
discharge should pass through sedimentation tanks prior to off-site discharge; ·
The
wastewater with a high concentration of SS should be treated (e.g. by sedimentation tanks with sufficient retention
time) before discharge. Oil
interceptors would also be required to remove the oil, lubricants and grease
from the wastewater; ·
Direct
discharge of the bentonite slurry (as a result of D-wall) is not
allowed. It should be reconditioned
and reused wherever practicable.
Temporary storage locations (typically a properly closed warehouse)
should be provided on site for any unused bentonite that needs to be
transported away after all the related construction activities area
completed. The requirements in ProPECC PN 1/94 should be adhered to in the handling and
disposal of bentonite slurries. |
To minimize
construction water quality impact from tunneling works |
Contractor |
All tunneling portion |
Construction stage |
·
Water
Pollution Control Ordinance ·
ProPECC PN 1/94 ·
TM-DSS ·
TM-EIAO |
·
Implemented |
|
S6.9.1.3 |
W3 |
Sewage
Effluent ·
Portable
chemical toilets and sewage holding tanks are recommended for handling the
construction sewage generated by the workforce. A licensed contractor should be employed to
provide appropriate and adequate portable toilets and be responsible for
appropriate disposal and maintenance. |
To minimize water
quality from sewage effluent |
Contractor |
All construction sites where practicable |
Construction stage |
·
Water
Pollution Control Ordinance ·
TM-DSS |
·
Implemented |
|
S6.9.1.5 |
W4 |
Groundwater
from Potential Contaminated Area: ·
No
direct discharge of groundwater from contaminated areas should be adopted. ·
A
discharge license under the WPCO through the Regional Office
of EPD for groundwater discharge should be applied. Prior to the excavation works within these potentially
contaminated areas, the groundwater quality should be reviewed
during the process of discharge license application. The
compliance to the Technical Memorandum on Standards for
Effluents Discharged into Drainage on
Sewerage Systems, Inland and Coastal Waters (TM-DSS) and the existence of
prohibited substance should be confirmed. If the
review results indicated that the groundwater to be
generated from the excavation works would be contaminated, the contaminated groundwater should be either
properly treated in compliance with the requirements
of the TM-DSS or properly recharged into the
ground. ·
If
wastewater treatment is deployed, the wastewater treatment unit shall deploy suitable treatment process (e.g. oil interceptor / activated
carbon) to reduce the pollution level to an acceptable standard and remove any prohibited substances
(e.g. TPH) to undetectable range. All treated effluent from
wastewater treatment plant shall meet the requirements as
stated in TM-DSS and should be discharged into the
foul sewers. ·
If
groundwater recharging wells are deployed, recharging wells should be installed as appropriate for recharging
the contaminated groundwater back into the ground.
The recharging wells should be selected at places
where the groundwater quality will not be
affected by the recharge operation as indicated in the Section 2.3 of TM-DSS. The baseline groundwater
quality shall be determined prior to the selection of the
recharge wells, and submit
a working plan (including the laboratory analytical results showing the quality of
groundwater at the proposed recharge location(s) as well as the pollutant
levels of groundwater to be recharged) to EPD for agreement. Pollution levels
of groundwater to be recharged shall not be higher than pollutant levels of ambient
groundwater at the recharge well. Prior to recharge, any prohibited
substances such as TPH products should be removed as necessary by installing
the petrol interceptor. |
To minimize groundwater
quality impact from contaminated area |
Contractor |
Excavation areas where contamination is found |
Construction stage |
·
Water
Pollution Control Ordinance ·
TM-DSS ·
TM-EIAO |
·
Implemented |
|
S6.9.1.6 |
W6 |
Accidental
Spillage In order to prevent
accidental spillage of chemicals, the following is recommended: ·
All
the tanks, containers, storage area should be bunded and the locations should
be locked as far as possible from the sensitive watercourse and stormwater drains; ·
The
Contractor should register as a chemical waste producer if chemical wastes
would be generated. Storage of
chemical waste arising from the construction activities should be stored with
suitable labels and warnings. Disposal of
chemical wastes should be conducted in compliance with the requirements as
stated in the Waste Disposal (Chemical Waste) (General) Regulation. |
To minimize water
quality impact from accidental spillage |
Contractor |
All construction site where practicable |
Construction stage |
·
Water
Pollution Control Ordinance ·
ProPECC PN 1/94 ·
TM-EIAO ·
TM-DSS |
·
Implemented,
deficiency rectified after observation. |
|
Waste Management (Construction Waste) |
|||||||||
S7.4.1 |
WM1 |
On-site
sorting of C&D material ·
Geological
assessment should be carried out by competent persons on site during
excavation to identify materials which are not suitable to use as aggregate
in structural concrete (e.g. volcanic rock, Aplite
dyke rock, etc.). Volcanic rock and
Aplite dyke rock should be separated at the source sites as far as
practicable and stored at designated stockpile area preventing them from
delivering to crushing facilities. The
crushing plant operator should also be reminded to set up measures to prevent
unsuitable rock from ending up at concrete batching plants and be turned into
concrete for structural use. Details
regarding control measures at source site and crushing facilities should be
submitted by the Contractor for the Engineer to review and agree. In addition, site records should also be
kept for the types of rock materials excavated and the traceability of delivery
will be ensured with the implementation of Trip Ticket System and enforced by
site supervisory staff as stipulated under DEVB TC(W) No. 6/2010 for tracking
of the correct delivery to the rock crushing facilities for processing into
aggregates. Alternative disposal
option for the reuse of volcanic rock and Aplite Dyke rock, etc. should be
explored. |
Separation of
unsuitable rock from ending up at concrete batching plants and be turned into
concrete for structural use |
Contractor |
All construction sites |
Construction stage |
·
DEVB
(W) No. 6/2010 |
·
Implemented |
|
S7.5.1 |
WM2 |
Construction
and Demolition Material ·
Maintain
temporary stockpiles and reuse excavated fill material for backfilling and reinstatement; ·
Carry
out on-site sorting; ·
Make
provisions in the Contract documents to allow and promote the use of recycled
aggregates where appropriate; ·
Adopt
‘selective demolition’ technique to demolish the existing structures and
facilities with a view to recovering broken concrete effectively for
recycling purpose, where possible; ·
Implement
a trip-ticket system for each works contract to ensure that the disposal of
C&D materials are properly documented and
verified; and ·
Implement
an enhanced Waste Management Plan similar to ETWBTC (Works) No. 19/2005 –
“Environmental Management on Construction Sites” to encourage on-site sorting
of C&D materials and to minimize their generation during the course of
construction. |
Good site practice
to minimize the waste generation and recycle the C&D materials as far as
practicable so as to reduce the amount for final disposal |
Contractor |
All construction sites |
Construction stage |
·
Land
(Miscellaneous Provisions) Ordinance ·
Waste
Disposal Ordinance ·
ETWB
TCW No. 19/2005 |
·
Implemented |
|
S7.5.1 |
WM3 |
C&D
Waste ·
Standard
formwork or pre-fabrication should be used as far as practicable in order to
minimize the arising of C&D materials.
The use of more durable formwork or plastic facing for the
construction works should be considered.
Use of wooden hoardings should not be used, as in other projects. Metal hoarding should be used to enhance
the possibility of recycling. The
purchasing of construction materials will be carefully planned in order to
avoid over ordering and wastage; ·
The
Contractor should recycle as much of the C&D materials as possible on-site.
Public fill and C&D waste should be segregated and stored in different
containers or skips to enhance reuse or recycling of materials and their
proper disposal. Where practicable,
concrete and masonry can be crushed and used as fill. Steel reinforcement bar can be used by
scrap steel mills. Different areas of
the sites should be considered for such segregation and storage. |
Good site practice
to minimize the waste generation and recycle the C&D materials as far as
practicable so as to reduce the amount for final disposal |
Contractor |
All construction sites |
Construction stage |
·
Land
(Miscellaneous Provisions) Ordinance ·
Waste
Disposal Ordinance ·
ETWB
TCW No. 19/2005 |
·
Implemented |
|
S7.5.1 |
WM5 |
Land-based
Sediment ·
All
construction plant and equipment shall be designed and maintained to minimize the risk of silt,
sediments, contaminants or other pollutants
being released into the water column or deposited
in the locations other than designated location; ·
All
vessels shall be sized such that adequate draft is maintained between vessels and the sea bed
at all states of the tide to ensure that undue
turbidity is not generated by turbulence from vessel
movement or propeller wash; ·
Before
moving the vessels which are used for transporting dredged material, excess material shall be
cleaned from the decks and exposed fittings of vessels
and the excess materials shall never be
dumped into the sea except at the approved locations; ·
Adequate
freeboard shall be maintained on barges to ensure that decks are not washed by wave action. ·
The
Contractors shall monitor all vessels transporting material to ensure that no dumping outside the approved
location takes place. The Contractor shall keep and
produce logs and other records to
demonstrate compliance and that journeys are consistent
with designated locations and copies of such records shall
be submitted to the engineers; ·
The
Contractors shall comply with the conditions in the dumping licence. ·
All
bottom dumping vessels (Hopper barges) shall be fitted with tight fittings seals to their bottom openings to
prevent leakage of material; ·
The
material shall be placed into the disposal pit by bottom dumping; ·
Contaminated
marine mud shall be transported by spit barge of not
less than 750m3 capacity and capable of rapid opening and discharge at the disposal site; ·
Discharge
shall be undertaken rapidly and the hoppers shall be closed immediately. Material adhering to the
sides of the hopper shall not be washed out of the hopper
and the hopper shall remain closed until
the barge returns to the disposal site. ·
For
Type 3 special disposal treatment, sealing of contaminant with geosynthetic containment before dropping
designated mud pit would be a possible arrangement. A
geosynthetic containment method is a method whereby the
sediments are sealed in geosynthetic containers and, the
containers would be dropped into the designated
contaminated mud pit where they would be covered by
further mud disposal and later by the mud pit
capping at the disposal site, thereby fulfilling the requirements for fully confined mud disposal. |
To control
pollution due to marine sediment |
Contractor |
Along CKR alignment |
Construction stage |
·
ETWB
TCW No. 34/2002 |
·
Implemented |
|
S7.5.1 |
WM6 |
Chemical
Waste ·
Chemical
waste that is produced, as defined by Schedule 1 of the Waste Disposal (Chemical
Waste) (General) Regulation, should be handled in accordance with the Code of
Practice on the Packaging, Labelling and Storage of Chemical Wastes; ·
Containers
used for the storage of chemical wastes should be suitable for the substance
they are holding, resistant to corrosion, maintained in a good condition, and
securely closed, have a capacity of less than 450 L unless the specification
has been approved by EPD, and display a label in English and Chinese in
accordance with instructions prescribed in Schedule 2 of the regulation; ·
The
storage area for chemical wastes should be clearly labelled and used solely
for the storage of chemical waste, enclosed on at least 3 sides, have an
impermeable floor and bunding of sufficient capacity to accommodate 110% of
the volume of the largest container or 20% of the total volume of waste
stored in that area, whichever is the greatest, have adequate ventilation,
covered to prevent rainfall entering, and arranged so that incompatible
materials are adequately separated; ·
Disposal
of chemical waste should be via a licensed waste collector, be to a facility
licensed to receive chemical waste, such as the Chemical Waste Treatment
Centre which also offers a chemical waste collection service and can supply
the necessary storage containers, or be to a reuser
of the waste, under approval from EPD.
|
Control the
chemical waste and ensure proper storage, handling and disposal |
Contractor |
All construction sites |
Construction stage |
·
Waste
Disposal (Chemical Waste) (General) Regulation ·
Code
of Practice on the Packaging, Labelling and Storage of Chemical Waste |
·
Implemented,
deficiency rectified after observation. |
|
S7.5.1 |
WM7 |
General
Refuse ·
General
refuse generated on-site should be stored in enclosed bins or compaction
units separately from construction and chemical wastes; ·
A
reputable waste collector should be employed by the Contractor to remove
general refuse from the site, separately from construction and chemical
wastes, on a daily basis to minimize odour, pest
and litter impacts. Burning of refuse
on construction sites is prohibited by law. ·
Aluminum
cans are often recovered from the waste stream by individual collectors if
they are segregated and made easily accessible. Separate labelled bins for their deposit
should be provided if feasible; ·
Office
wastes can be reduced through the recycling of paper if volumes are large
enough to warrant collection.
Participation in a local collection scheme should be considered by the
Contractor. |
Minimize production
of the general refuse and avoid odour, pest and
litter impacts |
Contractor |
All construction sites |
Construction stage |
·
Waste
Disposal Ordinance |
·
Implemented |
|
Land Contamination |
|
||||||||
S8.9 & Appendix 8.4 |
LC2 |
Excavation
of the Contaminated Soil ·
Prior
to commencement of the excavation works at the contamination zone, the zone
should be clearly marked out on site and the surface levels recorded.
Excavation of contaminated material should be undertaken using dedicated
earth-moving plant. ·
The
excavated contaminated soils would be stockpiled at designated area on site
and covered by sheet to prevent dispersion of contamination during
stockpiling. ·
The
Contractor should pay attention to the selection of suitable groundwater
lowering schemes and discharge points if the groundwater table is higher than
the contaminated soils during excavation. The Contractor should also obtain a
valid Water Pollution Control Ordinance (WPCO) discharge licence
from EPD where applicable. |
The contaminated
soil will be excavated for
on-site reuse |
Contractor |
PBH4 |
Prior to commencement of construction works
within the contaminated area |
·
Practice
Guide (PG)
for Investigation and Remediation of Contaminated Land ·
Guidance
Notes for Contaminated Land Assessment and Remediation ·
Guidance
Manual for Use of Risk-Based Remediation Goals (RBRGs) for Contaminated Land Management |
·
Implemented |
|
S8.9 & Appendix 8.4 |
LC3 |
·
Following
completion of the excavation to the specified depth, at least one sample from
the base of the excavation and four samples evenly
distributed along the boundary of the excavation
shall be taken for a closure assessment testing. The acceptance criterion is shown below:
·
If
the results of analysis below the RBRGs (Public Park), no further excavation will be required. If the analysis indicates presence of
contamination (i.e. noncompliance of the acceptance
criteria), further excavation shall be carried out in 0.5m increment
vertically and/or horizontally depending on the location(s) of the sample(s)
which has exceeded the acceptance criteria. Further sampling shall also be conducted
for compliance testing. The process of excavation, sampling and compliance testing
should continue until all contaminated materials are removed and should be
supervised by a Land Contamination Specialist. |
·
Implemented |
||||||
Appendix 8.4 |
LC4 |
A Remediation Report (RR) to
demonstrate adequate clean-up shall be prepared and submitted to EPD for
endorsement prior to the commencement of any construction/development works
within the sites. No construction/development works shall be carried out
prior to the endorsement of the RR by EPD. |
·
Implemented |
||||||
Hazard to Life |
|||||||||
S9.18 |
H1 |
Blasting activities regarding
transport and use of explosives should be supervised and audited by competent
site staff to ensure full compliance with the blasting permit conditions. |
To ensure that the
risks from the proposed explosives handling and transport would be acceptable |
Contractor |
Works areas at which explosives would be used |
Construction stage |
·
Dangerous
Goods Ordinance |
·
N/A |
|
S9.6, para.4 |
H2 |
Detonators shall not be transported
in the same vehicle with other Category 1 Dangerous Goods. |
To reduce the risk
of explosion during the transport of cartridged
emulsion |
Contractor |
- |
Construction stage |
·
Dangerous
Goods Ordinance |
·
N/A |
|
S9.6, para.8 |
H3 |
The explosives delivery trucks should
be approved by Mines Division and should meet the regulatory requirements for
transport of explosives. |
To comply with the
requirements for approval of an explosives delivery
vehicle |
Contractor |
- |
Construction stage |
·
Dangerous
Goods Ordinance |
·
N/A |
|
S9.10, para.7 and
S9.18 |
H4 |
Blast cover should be provided for
shaft at HMT, and kept closed during blasting. Provision of blast doors or heavy duty blast curtains should be implemented at the
shaft to prevent flyrock and control the air
overpressure. |
To ensure safe use
of explosives |
Contractor |
Shaft |
Construction stage |
- |
·
N/A |
|
S9.16 |
H5 |
Only the required quantity of
explosives for a particular blast should be transported to avoid the return. |
To reduce risks
during explosives transport |
Contractor |
Works areas at which explosives would be used |
Construction stage |
- |
·
N/A |
|
S9.18 |
H7 |
The approved truck dedicated for
transport of explosives should comply with the “Guidance Note on Requirements
for Approval of an Explosives Delivery Vehicle” issued by CEDD Mines
Division. The truck should be
periodically inspected and properly maintained in good operation
conditions. The fuel carried in the
fuel tank should be minimized to reduce the duration of fire. Adequate fire fighting
equipment shall be provided, inspected and replaced periodically (e.g. fire extinguishers). |
To reduce the risk
during explosives transport |
Contractor |
Works areas of which explosives would be used |
Construction stage |
·
Dangerous
Goods Ordinance |
·
N/A |
|
H8 |
The
driver and his assistant should be physically healthy, experienced and have
good safe driving records. The driver
should hold a proper driving licence for the
approved transport truck. Dedicated
training programme and regular road safety briefing
sessions/ workshops should be provided to enhance their safe driving attitude
and practice. Smoking should be
strictly prohibited. |
To reduce the risk during explosives
transport |
Contractor |
Works areas at which explosives would
be used |
Construction stage |
- |
·
N/A |
||
S9.18 |
H9 |
Emergency response plans in case of
road accident should be prepared and implemented. The driver and his assistant should be
familiar with the emergency procedures including evacuation, and proper
communication/ fire-fighting equipment should be provided to the driver and
his assistant. |
To reduce the risk
during explosives transport |
Contractor |
Works areas at which explosives would be used |
Construction stage |
- |
·
N/A |
|
S9.18 |
H10 |
Close liaison and communication among
Mines Division, Contractors for transport of explosives, and working staff of
the blasting should be established. In
case of any change of work schedule leading to cancellation or variation of
explosives required, relevant parties should be informed in time to avoid unused
explosives at the work sites. |
To reduce the risk
during explosives transport |
Contractor |
Works areas at which explosives would be used |
Construction stage |
- |
·
N/A |
|
S9.18 |
H11 |
Close liaison and communication with
Fire Services Department should be established to reduce the accidental
detonation escalated from a fire. The
contractors for transport of explosives should use the preferred transport
routes as far as practicable. |
To reduce the risk
during explosives transport |
Contractor |
Works areas at which explosives would be used |
Construction stage |
- |
·
N/A |
|
S9.18 |
H12 |
Contingency plan should be prepared
for transport of explosives under severe weather conditions such as
rainstorms and thunderstorms. |
To reduce the risk
during explosives transport |
Contractor |
Works areas at which explosives would be used |
Construction stage |
- |
·
N/A |
|
S9.18 |
H13 |
For explosive transport, all packages
of explosives on the truck should be properly stored in the truck compartment
as required. Packaging of the
explosives should remain intact (i.e. damage free)
until they are transferred to the blasting site. |
To reduce the risk
during explosives transport |
Contractor |
Works areas at which explosives would be used |
Construction stage |
- |
·
N/A |
|
S9.18 |
H14 |
Availability of a parking space
should be ensured before commencement of transport of explosives. Location for loading and unloading of
explosives should be as close as possible to the shaft. No hot work should be performed in the
vicinity during the time of loading and unloading. |
To reduce the risk
during explosives transport |
Contractor |
Works areas at which explosives would be used |
Construction stage |
- |
·
N/A |
|
S9.18 |
H22 |
It is recommended to explore to
minimize the use of the cartridged emulsion
explosives and maximize the use of bulk emulsion explosive as far as
practicable. |
To reduce the risk
during explosives transport |
Contractor |
Works areas at which explosives would be used |
Construction stage |
- |
·
N/A |
|
S9.18 |
H24 |
It is recommended to explore to use
smaller explosive charges such as ‘cast boosters’ or ‘mini-cast booster’
instead of cartridged emulsion as primers for bulk
emulsion. This option reduces the
quantity of explosives required for transportation for the sections where
bulk emulsion will be used. |
To reduce the risk
during explosives transport |
Contractor |
Works areas at which explosives would be used |
Construction stage |
- |
·
N/A |
|
Landscape & Visual |
|||||||||
S10.10.1 Table
10.11 |
LV3 |
Good Site Management ·
Large
temporary stockpiles of excavated material shall be covered with unobtrusive
sheeting to prevent dust and dirt spreading to adjacent landscape areas and
vegetation, and to create a neat and tidy visual appearance. ·
Construction
plant and building material shall be orderly and carefully stored in order to
create a neat and tidy visual appearance. |
Minimize visual impact |
Contractor |
Within Project site |
Construction stage |
- |
·
Implemented |
|
LV4 |
Screen Hoarding ·
Decorative
screen hoarding should be erected to screen the public from the construction
area. It should be designed to be
compatible with the existing urban context. |
Minimize visual impact |
Contractor |
Within Project site |
Construction stage |
- |
·
Implemented |
||
S10.10.1 Table
10.11 |
LV5 |
Lighting Control during Construction ·
All
lighting in the construction site shall be carefully controlled to minimize light
pollution and night-time glare to nearby residencies and GIC. The Contractor shall consider other
security measures, which shall minimize the visual impacts. |
Minimize visual
impact |
Contractor |
Within Project site |
Construction stage |
- |
·
N/A |
|
S10.10.1 Table
10.11 |
LV6 |
Erosion Control ·
The
potential for soil erosion shall be reduced by minimizing the extent of
vegetation disturbance on site and by providing a protective cover over newly
exposed soil. |
Minimize landscape
impact |
Contractor |
Within Project site |
Construction stage |
- |
·
N/A |
|
S10.10.1 Table
10.11 |
LV7 |
Tree Protection & Preservation ·
Carefully
protected during construction. Tree
protection measures will be detailed at the Tree Removal Application stage
and plans submitted to the relevant Government Department for approval in due
course in accordance with ETWB TC no. 3/2006. |
Minimize landscape
and visual impact |
Contractor |
Within Project site |
Construction stage |
·
‘Guidelines
for Tree Risk Management and Assessment Arrangement on an Area Basis and on a
Tree Basis’, Greening, Landscape and Tree Management (GLTM) Section, DEVB ·
Latest
recommended horticultural practices from GLTM Section, DEVB |
·
Implemented |
|
S10.10.1 Table
10.11 |
LV8 |
Tree Transplantation ·
For
trees unavoidably affected by the Project that have to be removed, where
practical transplantation will be chosen as the top priority method of
removal. If this is not possible or
practical compensatory planting will be provided for trees unavoidably felled
(See LV10). For trees unavoidably
affected by the Project works that are transplanted, transplantation must be
carried out in accordance with ETWB TCW 2/2004 and 3/2006. |
Minimize landscape
and visual impact |
Contractor |
Within Project site and designated off-site
locations |
Prior to Construction stage |
·
ETWB
TCW 3/2006 ·
Latest
recommended horticultural practices from Greening, Landscape and Tree
Management (GLTM) Section, DEVB ·
ETWB
TCW 2/2004 |
·
N/A |
|
S10.10.1 Table
10.11 |
LV9 |
Compensatory Planting ·
For
trees unavoidably affected by the Project that have to be removed, where
practical transportation will be chosen as the top priority method of removal
but if this is not possible or practical compensatory planting will be
provided for trees unavoidably felled.
All felled trees shall be compensated for by planting trees to the
satisfaction of relevant Government projects.
Required numbers and locations of compensatory trees shall be
determined and agreed separately with Government during the Tree Felling
Application process under ETWBTC 3/2006. ·
Compensatory
tree planting may be incorporated into public open spaces and along roadside
amenity areas affected by the construction works and therefore be part of the
bigger wider planting plans. Onsite
compensation planting is preferred but if necessary, additional receptor
sites outside the Works Area shall be agreed separately with Government
during the Tree Felling Application process. |
Minimize visual
impact and also enhance landscape |
Contractor |
Within Project site |
Construction stage |
·
ETWB
TCW 3/2006 ·
Latest
recommended horticultural practices from Greening, Landscape and Tree
Management (GLTM) Section, DEVB ·
ETWB
TCW 2/2004 |
·
N/A |
|
Cultural Heritage Impact (Construction Phase) |
|||||||||
S11.4.4 |
CH1 |
The
contractor should be alerted during the construction on the possibility of
locating archaeological remains and as a precautionary measure, AMO shall be
informed immediately in case of discovery of antiquities or supposed
antiquities in the subject sites. |
To preserve any
cultural heritage items which may be removed and damaged by the excavation |
Contractor |
During construction works for cut and cover tunnels |
Construction stage |
·
AMOs
requirements |
·
Implemented |
|
S12.6.1 |
CH3 |
·
Protective
covering should be provided for the buildings in the form
of plastic sheeting; ·
Buffer
zones should be provided between the construction works and the external walls of the buildings and
should be as large as site restrictions
allow and be marked out by temporary fencing or hoarding; ·
An
underpinning scheme is required to transfer the existing column loadings to a deeper rock stratum. The
supporting system includes cutting the existing ground
floor slab to expose the existing pile caps
and then construct transfer beams at both sides of
the pile caps. The transfer beams will tie up with the existing caps. Loadings of the transfer beams will be
transferred to the rock socket piles installed at the
two ends of the beams; ·
The
AAA settlement and tilting limit should be 6/8/10 mm and1/2000, 1/1500 and 1/1000; ·
Monitoring
of vibration levels will be undertaken during the construction
phase and the Alert, Alarm and Action (AAA) vibration limit will be set at
5/6/7.5 mm/s. The monitoring proposal should be
sent to AMO for comment;. ·
Regular
site inspections and monitoring works will be carried out by the contractor and the monitoring results will
be submitted to the resident site staff of HyD to ensure compliance. |
Protect the building from damage
from construction works |
Contractor |
Yau Ma Tei Police Station (Old Wing) (CKR-01) |
Prior to commencement of and during the
construction phase |
·
Guidelines
for Cultural Heritage Impact Assessment ·
EIAO-TM
Annex 10 and Annex 19 ·
AMO
Proposed Vibration Limits |
·
Implemented |
|
S12.6.1 |
|
·
Adopting
diaphragm wall construction method; ·
Grout
curtain should be provided in front of the building; ·
Recharging
system should be installed as a contingency measure
to mitigate the fluctuation of water table; ·
the
AAA settlement and tilting limit should be 6/8/10 mm and 1/2000, 1/1500 and 1/1000; ·
Monitoring
of vibration levels will be undertaken during the construction
phase and the Alert, Alarm and Action (AAA) vibration
limit will be set at 5/6/7.5 mm/s. The monitoring proposal
should be sent to AMO for comment;. ·
Regular
site inspections and monitoring works will be carried out by the contractor and the monitoring results will
be submitted to the resident site staff of HyD to ensure compliance. |
Protect the building from damage
from construction works |
Contractor |
Yau Ma Tei Police Station (Old Wing) (CKR-01) |
Prior to commencement of and during the
construction phase |
·
Guidelines
for Cultural Heritage Impact Assessment ·
EIAO-TM
Annex 10 and Annex 19 ·
AMO
Proposed Vibration Limits |
·
Implemented |
|
S12.6.1 Table 12.2 |
|
·
The
Alert, Alarm and Action (AAA) vibration limit will be set at 3/4/5 mm/s and a condition survey shall be
carried out by the project proponent prior to the
construction phase to confirm this assessment ·
Vibration
monitoring of the structure shall be employed during the construction phase to ensure that the level is
not exceeded. The monitoring proposal
should be sent to AMO for comment. |
Protect the building from damage
from construction works |
Contractor |
Tin Hau Temple (CKR-02) |
Prior to commencement of and during the
construction phase |
·
Guidelines
for Cultural Heritage Impact Assessment ·
EIAO-TM
Annex 10 and Annex 19 ·
AMO
Proposed Vibration Limits |
·
Implemented |
|
EM&A Project |
|||||||||
S13.2 |
EM1 |
An
Independent Environmental Checker needs to be employed as per the EM&A
Manual |
Control EM&A
Performance |
Highways Department |
All construction sites |
Construction stage |
·
EIAO
Guidance Note No. 4/2010 ·
TM-EIAO |
·
Implemented |
|
S13.2-13.4 |
EM2 |
·
An
Environmental Team needs to be employed as per the EM&A Manual; ·
Prepare
a systematic Environmental Management Plan to ensure effective implementation
of the mitigation measures; ·
An
environmental impact monitoring needs to be implemented by the Environmental
Team to ensure all the requirements given in the EM&A Manual are fully
complied with. |
Perform
environmental monitoring & auditing |
Highways Department/ Contractor |
All construction sites |
Construction stage |
·
EIAO
Guidance Note No. 4/2010 ·
TM-EIAO |
·
Implemented |
|
Appendix G
Monitoring
Schedule of the Reporting Month
Remark: Noise monitoring at the Coronation Tower 1
(W-P11) was temporarily suspended on 27 January 2021 due to a case of novel
coronavirus infection at the Coronation Circle on 17 January 2021. Temporary
alternative noise monitoring location, W-P11-T was used to conduct noise
monitoring on 27 January 2021. TSP monitoring at Man
Cheong Building (W-A6), noise monitoring at Hydan
Place (W-N18), and noise monitoring at Prosperous Garden Block 1
(W-N25A/W-N25A-T) were temporarily suspended from 27 January 2021 to 9 February
2021 as these stations were located inside or in proximity to the specified
areas.
Appendix H
Calibration
Certificates
(Air Monitoring)
Appendix I
Calibration Certificates (Noise)
Appendix J
The Certification of Laboratory with HOKLAS Accredited Analytical Tests
Appendix K
Location Plan of Noise and Air
Quality Monitoring Station
Appendix L
Monitoring Data (Air Monitoring)
Location: |
Yau Ma Tei Catholic Primary School (Hoi Wang Road) ( W-A1) |
Monitoring date:
|
4, 9,
15, 21, 27 January 2021 |
Parameter
: |
TSP 1-hour |
Other Factors |
Nearby traffic |
Date |
1-hour TSP (μg/m3) |
||||
Weather |
Start Time |
1st Hour (μg/m3) |
2nd Hour (μg/m3) |
3rd Hour (μg/m3) |
|
04/01/2021 |
Cloudy |
11:39 |
37 |
47 |
45 |
09/01/2021 |
Cloudy |
16:18 |
53 |
48 |
42 |
15/01/2021 |
Sunny |
13:34 |
44 |
56 |
57 |
21/01/2021 |
Sunny |
13:31 |
53 |
63 |
46 |
27/01/2021 |
Sunny |
10:40 |
43 |
49 |
55 |
Location: |
Man
Cheong Building (W-A6) |
Monitoring date:
|
4, 9,
15, 21 January 2021 |
Parameter
: |
TSP 1-hour |
Other Factors |
Nearby traffic |
Date |
1-hour TSP (μg/m3) |
||||
Weather |
Start Time |
1st Hour (μg/m3) |
2nd Hour (μg/m3) |
3rd Hour (μg/m3) |
|
04/01/2021 |
Cloudy |
9:20 |
49 |
43 |
41 |
09/01/2021 |
Cloudy |
16:12 |
43 |
50 |
47 |
15/01/2021 |
Sunny |
16:18 |
53 |
51 |
44 |
21/01/2021 |
Sunny |
9:38 |
63 |
50 |
46 |
27/01/2021^ |
Sunny |
Suspension
of monitoring due to COVID-19 |
^Remark: 1-hour TSP monitoring at W-A6
was temporarily suspended from 27 January 2021 to 9 February 2021 as this
station was located inside the specified area of lock down due to COVID-19.
Figure 1: Graphical Illustration of Measured 1-hour TSP (μg/m3) Levels at W-A1
Figure 2: Graphical Illustration of Measured
1-hour TSP (μg/m3) Levels at W-A6
Remark: 1-hour TSP monitoring at W-A6
was temporarily suspended from 27 January 2021 to 9 February 2021 as this
station was located inside the specified area.
Location: |
Yau Ma Tei Catholic
Primary School (Hoi Wang Road) (W-A1) |
Monitoring date: |
4, 9, 15, 21, 27 January 2021 |
Parameter : |
TSP 24-hour |
Other Factors |
Nearby traffic |
|
|
Location: |
Man
Cheong Building (W-A6) |
Monitoring date:
|
4, 9,
15, 21 January 2021 |
Parameter
: |
TSP 24-hour |
Other Factors |
Nearby traffic |
|
|
|
|
^Remark: 24-hour TSP monitoring at
W-A6 was temporarily suspended from 27 January 2021 to 9 February 2021 as this
station was located inside the specified area of lock down due to COVID-19.
Figure 3: Graphical Illustration of Measured 24-hour
TSP (μg/m3) Levels at W-A1
Figure 4: Graphical Illustration of Measured 24-hour
TSP (μg/m3) Levels at W-A6
Remark: 24-hour TSP monitoring at W-A6
was temporarily suspended from 27 January 2021 to 9 February 2021 as this
station was located inside or in proximity to the specified areas.
Wind direction data for 4, 5, 9, 10, 15, 16, 21, 22, 27, 28 January 2021
Wind speed data for 4, 5, 9, 10, 15, 16, 21, 22, 27, 28 January 2021
Appendix M
Monitoring Data (Noise)
Location: |
Yau Ma Tei Catholic Primary School (Hoi Wang Road) (W-N1A) |
Monitoring date:
|
4, 9,
15, 21, 27 January 2021 |
Parameter
: |
Leq, L10,
L90 |
Other Factors |
Nearby traffic |
Noise Monitoring data:
Date |
Weather |
Start Time |
- |
End Time |
Leq |
L10 |
L90 |
Wind speed (m/s) |
04/01/2021 |
Cloudy |
11:37 |
- |
12:07 |
60.7 |
62.9 |
57.8 |
2.8 |
09/01/2021 |
Cloudy |
16:13 |
- |
16:43 |
62.6 |
69.4 |
57.2 |
1.6 |
15/01/2021 |
Sunny |
13:38 |
- |
14:08 |
59.5 |
60.8 |
56.7 |
1.7 |
21/01/2021 |
Sunny |
13:37 |
- |
14:07 |
63.1 |
63.7 |
57.9 |
1.7 |
27/01/2021 |
Sunny |
10:40 |
- |
11:10 |
61.4 |
63.9 |
57.9 |
2.3 |
Location: |
Hydan
Place (W-N18) |
Monitoring date:
|
4, 9,
15, 21 January 2021 |
Parameter
: |
Leq, L10, L90 |
Other Factors |
Nearby traffic |
Noise Monitoring data:
Date |
Weather |
Start Time |
- |
End Time |
Leq |
L10 |
L90 |
Wind speed (m/s) |
04/01/2021 |
Cloudy |
13:32 |
- |
14:02 |
69.3 |
72.2 |
67.4 |
1.7 |
09/01/2021 |
Cloudy |
14:16 |
- |
14:46 |
69.7 |
72.5 |
62.5 |
1.3 |
15/01/2021 |
Sunny |
18:05 |
- |
18:35 |
66.3 |
67.3 |
65.1 |
0.3 |
21/01/2021 |
Sunny |
12:33 |
- |
13:03 |
65.2 |
68.1 |
62.6 |
2.6 |
27/01/2021^ |
Sunny |
Suspension
of monitoring due to COVID-19 |
^Remark: Noise monitoring at W-N18 was
temporarily suspended from 27 January 2021 to 9 February 2021 as this station
was located inside the specified area of lock down due to COVID-19.
Location: |
Prosperous
Garden Block 1 (W-N25A) |
Monitoring date:
|
4, 9,
15, 21 January 2021 |
Parameter
: |
Leq, L10, L90 |
Other Factors |
Nearby traffic |
Noise Monitoring data:
Date |
Weather |
Start Time |
- |
End Time |
Leq |
L10 |
L90 |
Wind speed (m/s) |
04/01/2021 |
Cloudy |
11:12 |
- |
11:42 |
70.2 |
72.0 |
68.0 |
0.8 |
09/01/2021 |
Cloudy |
11:08 |
- |
11:38 |
64.7 |
68.5 |
57.4 |
0.9 |
15/01/2021 |
Sunny |
11:10 |
- |
11:40 |
70.2 |
72.0 |
67.7 |
3.3 |
21/01/2021 |
Sunny |
10:57 |
- |
11:27 |
68.8 |
71.9 |
65.0 |
3.1 |
27/01/2021^ |
Sunny |
Suspension
of monitoring due to COVID-19 |
^Remark; Noise monitoring at
W-N25A/W-N25A-T were temporarily suspended from 27 January 2021 to 9 February
2021 as these stations were located inside or in proximity to the specified
areas of lock down due to COVID-19.
Location: |
The Coronation
Tower 1 (W-P11), Roadside in front of The Hong Kong Police
Force Yau Ma Tei Divisional Station (W-P11-T) |
Monitoring date:
|
4, 9,
15, 21, 27 January 2021 |
Parameter
: |
Leq, L10, L90 |
Other Factors |
Nearby traffic |
Noise Monitoring data:
Date |
Weather |
Start Time |
- |
End Time |
Leq |
L10 |
L90 |
Wind speed (m/s) |
04/01/2021 |
Cloudy |
10:26 |
- |
10:56 |
69.9 |
72.3 |
65.0 |
1.1 |
09/01/2021 |
Cloudy |
10:10 |
- |
10:40 |
68.3 |
70.4 |
65.5 |
1.9 |
15/01/2021 |
Sunny |
9:10 |
- |
9:40 |
66.2 |
67.8 |
64.0 |
3.1 |
21/01/2021 |
Sunny |
9:22 |
- |
9:52 |
68.9 |
71.0 |
65.3 |
2.7 |
27/01/2021^ |
Sunny |
15:04 |
- |
15:34 |
71.0 |
71.8 |
69.7 |
3.6 |
^Remark: Noise monitoring at the
Coronation Tower 1 (W-P11) was temporarily suspended on 27 January 2021 due to
a case of novel coronavirus infection at the Coronation Circle on 17 January
2021. A temporary alternative noise monitoring location, W-P11-T was used on 27
January 2021. A correction of +3dB(A) was made to the free field measurement for
W-P11-T.
Figure 1: Graphical Illustration of Measured Noise Levels at W-N1A
Figure 2: Graphical Illustration of Measured Noise Levels at W-N18
Remark: Noise monitoring at W-N18 was
temporarily suspended from 27 January 2021 to 9 February 2021 as this station
was located inside the specified area.
Figure 3: Graphical Illustration of Measured Noise
Levels at W-N25A
Remark; Noise monitoring at
W-N25A/W-N25A-T were temporarily suspended from 27 January 2021 to 9 February
2021 as these stations were located inside or in proximity to the specified
areas.
Figure 4: Graphical Illustration of Measured Noise
Levels at W-P11
Remark: Noise monitoring at the
Coronation Tower 1 (W-P11) was temporarily suspended on 27 January 2021 due to
a case of novel coronavirus infection at the Coronation Circle on 17 January
2021. A temporary alternative noise monitoring location, W-P11-T was used on 27
January 2021. A correction of +3dB(A) was made to the free field measurement for
W-P11-T.
Appendix N
Waste Flow Table
Monthly Summary Waste Flow Table
Name of Department: Highways Department Contract
No. / Works Order No.: __HY/2014/08__
Monthly
Summary Waste Flow Table for January 2021
[to be submitted
not later than the 15th day of each month following reporting month] (All quantities shall be rounded
off to 1 decimal place.)
Month |
|
Actual Quantities of Inert Construction Waste Generated Monthly |
|||||||||||||
(a)=(b)+(c)+(d)+(e)+
(f)+ (g)+ (h)+ (i)+ (j)+ (k) Total Quantity Generated |
(b) Hard Rock and Large Broken Concrete |
(c) Reused in the Contract |
(d) Reused in other Projects |
(e) Disposed of as Public Fill |
(f) Imported Fill |
||||||||||
(in ‘tonnes) |
(in ‘tonnes) |
(in ‘tonnes) |
(in ‘tonnes) |
(in ‘tonnes) |
(in ‘tonnes) |
||||||||||
Jan-21 |
9228.8 |
856.6 |
0.0 |
0.0 |
8262.2 |
0.0 |
|||||||||
Feb-21 |
|
|
|
|
|
|
|||||||||
Mar-21 |
|
|
|
|
|
|
|||||||||
Apr-21 |
|
|
|
|
|
|
|||||||||
May-21 |
|
|
|
|
|
|
|||||||||
Jun-21 |
|
|
|
|
|
|
|||||||||
Sub-total |
9228.8 |
856.6 |
0.0 |
0.0 |
8262.2 |
0.0 |
|||||||||
Jul-21 |
|
|
|
|
|
|
|||||||||
Aug-21 |
|
|
|
|
|
|
|||||||||
Sep-21 |
|
|
|
|
|
|
|||||||||
Oct-21 |
|
|
|
|
|
|
|||||||||
Nov-21 |
|
|
|
|
|
|
|||||||||
Dec-21 |
|
|
|
|
|
|
|||||||||
Total |
9228.8 |
856.6 |
0.0 |
0.0 |
8262.2 |
0.0 |
|||||||||
2018 |
51057.9 |
0.0 |
0.0 |
0.0 |
47715.6 |
2877.4 |
|||||||||
2019 |
112830.1 |
541.0 |
1523.8 |
13525.0 |
93132.9 |
3155.6 |
|||||||||
2020 |
193021.9 |
58778.0 |
1205.6 |
19108.6 |
112556.8 |
0.0 |
|||||||||
Accumulated Total |
366138.7 |
60175.6 |
2729.4 |
32633.6 |
261667.5 |
6033.0 |
|||||||||
|
|
|
|
|
|
|
|
|
|||||||
Month |
Actual Quantities of Non-inert Construction Waste
Generated Monthly |
||||||||
(g) Metals |
(h) Paper/ cardboard packaging |
(i) Plastics |
(j) Chemical Waste |
(k) Others, e.g. General Refuse disposed at Landfill |
|||||
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘000kg) |
(in ‘tonnes) |
|||||
generated |
recycled |
generated |
recycled |
generated |
recycled |
generated |
recycled |
generated |
|
Jan-21 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
20.7 |
0.0 |
89.3 |
Feb-21 |
|
|
|
|
|
|
|
|
|
Mar-21 |
|
|
|
|
|
|
|
|
|
Apr-21 |
|
|
|
|
|
|
|
|
|
May-21 |
|
|
|
|
|
|
|
|
|
Jun-21 |
|
|
|
|
|
|
|
|
|
Sub-total |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
20.7 |
0.0 |
89.3 |
Jul-21 |
|
|
|
|
|
|
|
|
|
Aug-21 |
|
|
|
|
|
|
|
|
|
Sep-21 |
|
|
|
|
|
|
|
|
|
Oct-21 |
|
|
|
|
|
|
|
|
|
Nov-21 |
|
|
|
|
|
|
|
|
|
Dec-21 |
|
|
|
|
|
|
|
|
|
Total |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
20.7 |
0.0 |
89.3 |
2018 |
28.4 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
2.0 |
0.0 |
434.5 |
2019 |
0.0 |
9.1 |
3.4 |
6.8 |
0.0 |
0.0 |
5.2 |
0.0 |
927.3 |
2020 |
69.2 |
0.0 |
3.3 |
0.0 |
0.02 |
0.0 |
25.3 |
0.0 |
1275.1 |
Accumulated Total Total Total |
97.6 |
9.1 |
6.7 |
6.8 |
0.02 |
0.0 |
53.2 |
0.0 |
2726.2 |
Appendix O
Statistics
on Complaint, Notifications of Summons and Successful Prosecutions
Statistical Summary of Exceedances
Air
Quality |
|||
Location |
Action Level |
Limit Level |
Total |
W-A1 |
0 |
0 |
0 |
W-A6 |
0 |
0 |
0 |
Noise |
|||
Location |
Action Level |
Limit Level |
Total |
W-N1A |
0 |
0 |
0 |
W-N18 |
1^ |
0 |
1 |
W-N25A |
0 |
0 |
0 |
W-P11 |
0 |
0 |
0 |
Remark: 1) ^W-N18 was the
nearest NSR to Zone D2 and D3.
Statistical Summary of
Environmental Complaints
Reporting Period |
Environmental Complaint Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
|
1 January 2021- 31 January 2021 |
1 |
20 |
Construction Noise |
Statistical Summary of
Environmental Non-compliance
Reporting Period |
Environmental Non-compliance Statistics |
||
Frequency |
Cumulative |
Details |
|
1 January 2021- 31 January 2021 |
0 |
1 |
N/A |
Statistical Summary of
Environmental Summons
Reporting Period |
Environmental Summons Statistics |
||
Frequency |
Cumulative |
Details |
|
1 January 2021- 31 January 2021 |
0 |
1 |
N/A |
Statistical Summary of
Environmental Prosecution
Reporting Period |
Environmental Prosecution Statistics |
||
Frequency |
Cumulative |
Details |
|
1 January 2021- 31 January 2021 |
0 |
0 |
N/A |
Appendix P
Monitoring
Schedule of the Coming Month
Remark: TSP monitoring at Man
Cheong Building (W-A6), noise monitoring at Hydan
Place (W-N18), and noise monitoring at Prosperous Garden Block 1
(W-N25A/W-N25A-T) were temporarily suspended from 27 January 2021 to 9 February
2021 as these stations were located inside or in proximity to the specified
areas.
Appendix Q
Interim
Report for the Complaint