I.
Introduction
This
is the 5th Monthly EM&A Report prepared by Fugro Technical
Services Limited for the Contract no. HY/2018/08 Central Kowloon Route ¡V
Central Tunnel. The Contract no. HY/2018/08 commenced on 19 September 2019. This
report summarized the monitoring results and audits findings of the EM&A
programme under the issued EP (EP No.: EP-457/2013/C) and in accordance with
the EM&A Manual during the reporting period from 01/01/2020 to 31/01/2020.
II.
Summary
of Main Works Undertaken and Key Measures Implemented
The main construction
works carried out in the reporting period were as follow:
¡P
Prebored
H piling for ventilation shaft;
¡P
Formation
of site haul road leading to Chung Hau Street;
¡P
Initial
tunnel excavation for construction adit;
¡P
Mucking
out from tunnel;
¡P
Construction
of CLP transformer room;
¡P
Site
installation and utilities diversion;
¡P
Erection
of main site office.
III.
Summary
of Exceedances, Investigation and Follow-up
No Action or Limit
Level Exceedance was recorded in the reporting period.
IV.
Complaint
Handling, Prosecution and Public Engagement
No complaints,
notification of summons and prosecutions were received in the reporting period.
No public engagement
activities were conducted in the reporting period.
V.
Reporting
Change
There were no
reporting changes during the reporting month.
VI.
Future
Key Issues
The main works will be
anticipated in the next reporting period are as follow:
¡P
Prebored
H piling for ventilation shaft;
¡P
Formation
of site haul road leading to Chung Hau Street;
¡P
Removal
of oversized tree extending to Chung Hau Street;
¡P
Initial
tunnel excavation for construction adit;
¡P
Mucking
out from tunnel;
¡P
Construction
of CLP transformer room;
¡P
Site
installation and utilities diversion;
¡P
Erection
of main site office.
The
recommended mitigation measures corresponding to the main works in the next
reporting period are listed as follow:
¡P
Mitigation
measures in form of regular watering under a good site practice should be
adopted, particularly for the earthwork and breaking activities;
¡P
Any
excavated, stockpile of dusty material or load of dusty materials on a vehicle
leaving a construction site should be covered entirely by impervious sheeting;
¡P
All
construction plants / machineries should be checked / serviced on a regular
basis during the courses of construction to minimize the emission of noise
generation and eliminate dark smoke emission;
¡P
All
C&D materials generated should be transported and stored at temporary
storage area. Suitable materials should be sorted for reuse on-site;
¡P
Wastewater
generated from drilling shall be properly collected for reuse or treated by
wastewater treatment facilities before discharge;
¡P
Provision
of drip trays for equipment likely cause spillage of chemical / fuel, and
provide routine maintenance;
¡P
Erecting
temporary noise barrier for noisy Powered Mechanical Equipment (PME) and
deployment of Quality Powered Mechanical Equipment (QPME) as many as
practicable;
¡P
Mitigation
measures recommended in the Landscape Mitigation Plan shall be implemented for
felling trees;
¡P
Conditions
in the Environmental Permit and License should be followed;
¡P
All
recommended mitigation measures specified in the approved EIA Report and
EM&A Manual shall be implemented.
The
following EP submissions (EP-457/2013/C) were submitted during the reporting
month:
Table I Status
of Required Submission under Environmental Permit
EP Condition |
Submission |
Submission
Date |
3.4 |
Monthly EM&A Report (December 2019) |
14 January 2020 |
Contents
1.3 Construction Programme and Activities
1.4 Works undertaken during the month
1.5 Status of Environmental Licences, Notification and Permits
2.1 Construction Dust and Noise Monitoring Location
2.2 Construction Dust Monitoring
2.3 Construction Noise Monitoring
2.4 Construction Dust and Noise Monitoring Schedule
2.5 The Action and Limit Levels
3.1 Construction Dust Monitoring
3.2 Construction Noise Monitoring
5.1 Complaint Handling, Prosecution and
Public Engagement
5.2 Summary of Environmental
Non-Compliance
Tables
Table I ¡V Status of Required Submission under
Environmental Permit
Table 1.1 ¡V Contact Information of Key Personnel
Table 1.2 ¡V Environmental Licenses, Notification and
Permits Summary
Table 2.1 ¡V Construction Dust and Noise Monitoring
Location
Table 2.2 ¡V Construction Dust Monitoring Equipment
Table 2.3 ¡V Construction Noise Monitoring
Parameters, Frequency and Duration
Table 2.4 ¡V Construction Noise Monitoring Equipment
Table 3.1 ¡V Summary of 1-hour TSP Monitoring Results
in the Reporting Period
Table 3.2 ¡V Summary of 24-hour TSP Monitoring
Results in the Reporting Period
Table 3.3 ¡V Summary of Construction Noise Monitoring
Results in the Reporting Period
Table 4.1 ¡V Observations and Recommendation of Site
Inspection in the Reporting Period 10
Table 6.1 ¡V Status of Required Submission under
Environmental Permit
Figures
Figure 1 The Site Layout Plan
of the Contract
Figure 2 The Location of the
Construction Dust and Noise Monitoring Station
Appendix A Construction Programme
Appendix B Project
Organization Chart
Appendix C Calibration
Certificate for Construction Dust Monitoring Equipment
Appendix D Calibration
Certificate for Construction Noise Monitoring Equipment
Appendix E Environmental
Monitoring Schedule
Appendix F Action
and Limit Levels for Construction Dust and Noise Monitoring
Appendix G Construction
Dust Monitoring Results and Meteorological Observations
Appendix H Construction
Noise Monitoring Results
Appendix I Event
and Action Plan
Appendix J Implementation
Status of Environment Mitigation Measures (Construction Phase)
1.1.1 In order to
meet the traffic demand and relieve traffic congestion on the existing
east-west roads across Central Kowloon, Central Kowloon Route (CKR)
(hereinafter referred to as ¡§the Project¡¨) is proposed which is a 4.7 km long
dual 3-lane trunk road in Central Kowloon linking Yau Ma Tei Interchange in
West Kowloon with the road network on Kai Tak Development and Kowloon Bay in
East Kowloon.
1.1.2 The Central
Kowloon Route ¡V Design and Construction Environmental Impact Assessment Report
(Register No.: AEIAR-171/2013) was approved with conditions by the
Environmental Protection Department (EPD) on 11 July 2013. An Environmental
Permit (EP-457/2013) was issued on 9 August 2013. Variations of EP (VEP) was
subsequently applied for and the latest EP (EP-457/2013/C) was issued by EPD on
16 January 2017.
1.1.3 Contract
no. HY/2018/08 Central Kowloon Route ¡V Central Tunnel (hereinafter referred to
as ¡§the Contract¡¨), is one of the contracts of CKR which included the
construction of the central tunnel, cut-and-cover tunnels at Yau Ma Tei and Ma
Tau Kok and construction of piles and diaphragm walls for Ho Man Tin
ventilation building.
1.1.4 Fugro
Technical Services Limited (FTS) was appointed by Bouygues Travaux Publics
(BTP) as the Environmental Team (ET) under the Contract no. HY/2018/08) to
execute the environmental monitoring and audit (EM&A) programme under the
issued EP (EP No.: EP-457/2013/C) and in accordance with the EM&A Manual.
1.1.5 This is the
5th Monthly EM&A Report prepared by FTS for the Contract no.
HY/2018/08 Central Kowloon Route ¡V Central Tunnel. The Contract no. HY/2018/08
commenced on 19 September 2019. This report summarized the monitoring results
and audits findings of the EM&A programme under the issued EP (EP No.:
EP-457/2013/C) and in accordance with the EM&A Manual during the reporting
period from 01/01/2020 to 31/01/2020.
1.2.1 The Project
Organization structure is shown in Appendix B. The key personnel contact
names and numbers are summarized in Table 1.1.
Table 1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Highways Department (HyD) |
E13/CKR |
Mr. Joe Lam |
2762 3380 |
Arup-Mott MacDonald Joint Venture (AMMJV) |
Senior Resident Engineer |
Mr. Ben Poon |
3619 5967 |
ERM-Hong Kong, Limited (ERM) |
Independent Environmental
Checker (IEC) |
Ms. Mandy To |
2271 3000 |
Bouygues Travaux Publics (BTP) |
Environmental
Manager |
Mr. Simon Wong |
9281 4346 |
Fugro Technical Services Limited |
ET Leader |
Mr. David Hung |
3565 4371 |
1.3 Construction
Programme and Activities
1.3.1 The
construction phase of this Contract under the EP was commenced in October 2019.
The site layout plan of the Contract is shown in Figure 1.
1.3.2 The
construction programme of this Contract is shown in Appendix A.
1.4 Works
undertaken during the month
1.4.1 The
main construction works carried out in the reporting period were as follow:
¡P
Prebored
H piling for ventilation shaft;
¡P
Formation
of site haul road leading to Chung Hau Street;
¡P
Initial
tunnel excavation for construction adit;
¡P
Mucking
out from tunnel;
¡P
Construction
of CLP transformer room;
¡P
Site
installation and utilities diversion;
¡P
Erection
of main site office.
1.5 Status
of Environmental Licences, Notification and Permits
1.5.1 A summary
of the relevant permits, licenses and/or notifications on environmental
protection for this Contract is presented in Table 1.2.
Table 1.2 Environmental
Licenses, Notification and Permits Summary
Permit/ Notification/ License |
Reference No |
Valid From |
Valid Till |
Form NB |
448930, 448970, 448971 |
Mid-Sep 2019 |
NA |
Billing Account for Disposal of C&D
waste |
Account
no. 7034790 |
6 Aug 2019 |
NA |
Chemical Waste Producer Registration |
5111-236-B2557-02 |
25 Sep 2019 |
NA |
Construction Noise Permit |
GW-RE0785-19 |
4 Oct 2019 |
3 Jan 2020 |
GW-RE1081-19 |
6 Jan 2020 |
1 Jun 2020 |
|
Water Discharge License |
WT00034873-2019 |
22 Nov 2019 |
30 Nov 2024 |
2. ENVIRONMENTAL MONITORING REQUIREMENTS
2.1 Construction
Dust and Noise Monitoring Location
2.1.1 The
monitoring station for construction dust and noise monitoring pertinent to the
Project has been identified based on the approved EM&A Manual for the
Project. The location of the construction dust and noise monitoring station is
summarized in Table 2.1 and displayed in Figure 2.
Table 2.1
Construction Dust and Noise Monitoring Location
Dust
Monitoring Station ID |
Noise
Monitoring Station ID |
Monitoring
Location |
M-A3 |
M-N3 |
SKH Tsoi Kung Po Secondary School |
Notes:
1. The dust and noise monitoring station
proposed in the EM&A Manual (i.e. Ko Fai House, Kwun Fai Court with ID:
M-A6/ M-N6) was not available for impact dust and noise monitoring, therefore
impact monitoring was conducted at M-A3/M-N3 as an alternative which was agreed
by the ER, IEC and EPD;
2. The coordinates of SKH Tsoi Kung Po
Secondary School can be represented as follow:
Latitude: 22.314719, Longitude: 114.180694
(HK80 Geographical Coordinates)
2.2 Construction
Dust Monitoring
Monitoring Requirement
2.2.1 In
accordance with the approved EM&A Manual, 1-hour and 24-hour Total
Suspended Particulates (TSP) levels should be measured at the designated air
quality monitoring stations to indicate the impacts of construction dust on air
quality. Regular Impact 24-hour TSP monitoring should be carried out for at
least once every 6 days, and 1-hour TSP monitoring should be done at least 3
times every 6 days when the highest dust impact occurs.
Monitoring Equipment
2.2.2 24-hour TSP
air quality monitoring was performed using High Volume Sampler (HVS) deployed
at the designated monitoring station. The HVS shall meet all the requirements
of the EM&A Manual.
2.2.3 A portable
direct reading dust meter was used to carry out the 1-hour TSP monitoring.
2.2.4 The model
of the dust monitoring equipment used is summarized in Table 2.2.
Table 2.2 Construction
Dust Monitoring Equipment
Equipment |
Brand |
Model |
Serial No. |
High Volume Sampler (24-hour TSP) |
Tisch |
TE-5170 |
4388 |
Portable direct reading dust meter (1-hour
TSP) |
Sibata |
Model LD-3B |
647594 |
Monitoring Methodology for HVS
2.2.5 The
following guidelines were adopted during the installation of HVS:
¡P
Sufficient
support is provided to secure the samplers against gusty wind.
¡P
No
two samplers are placed less than 2 meters apart.
¡P
The
distance between the sampler and an obstacle, such as buildings, is at least
twice the height that the obstacle protrudes above the sampler.
¡P
A
minimum of 2 meters of separation from walls, parapets and penthouses is required
for rooftop samples.
¡P
A
minimum of 2 meters separation from any supporting structure, measured
horizontally is required.
¡P
No
furnaces or incineration flues are nearby.
¡P
Airflow
around the samplers is unrestricted.
¡P
The
samplers are more than 20 meters from the drip line.
¡P
Any
wire fence and gate, to protect the sampler, should not cause any obstruction
during monitoring.
¡P
Permission
must be obtained to set up the samplers and to obtain access to the monitoring
stations.
¡P
A
secured supply of electricity is needed to operate the samplers.
2.2.6 Prior to
the commencement of the dust sampling, the flow rate of the high volume sampler
shall be properly set. The power supply should be checked to ensure the proper
functioning of the sampler. The sampler is recommended to be operated for 5
minutes to establish thermal equilibrium before placing any filter media at the
designated air monitoring station.
2.2.7 The filter
holding frame should be removed by loosening the four nuts and placing
carefully a weighted and conditioned filter at the centre with the stamped
number upwards on a supporting screen.
2.2.8 The filter
should be aligned on the screen so that the gasket formed an airtight seal on
the outer edges of the filter. The filter holding frame should be tightened to
the filter holder with swing bolts. The applied pressure should be sufficient
to avoid air leakage at the edges.
2.2.9 A
programmed timer should be used to control the duration of operation.
Information should be recorded on the record sheet, which included the starting
time, the weather condition and the filter number.
2.2.10 After sampling process
is finished, the filter should be removed and sent to the laboratory for
weighting. The elapsed time should also be recorded.
2.2.11 All filters should be equilibrated
in a conditioning environment for 24 hours before weighting. The conditioning
environment temperature should be between 25¢XC and 30¢XC and not vary by more
than ¡Ó3¢XC; the relative
humidity (RH) should be <50% and not vary by more than ¡Ó5%.
A convenient working RH is 40%.
Maintenance and Calibration for HVS
2.2.12 The high volume motors
and their accessories should be properly maintained, including routine motor
brushes replacement and electrical wiring checking, to ensure that the
equipment and a continuous power supply were in good working condition.
2.2.13 Initial calibration of
dust monitoring equipment shall be conducted upon installation and thereafter
at fortnightly intervals. The transfer standard shall be traceable to the
internationally recognized primary standard and be calibrated annually. The
calibration certificate for the HVS is provided in Appendix C.
Monitoring Methodology for Direct Reading Dust Meter
2.2.14 Portable Laser Particle
Photometer Monitors should be operated in accordance with the Manufacturer¡¦s
instruction Manual as below:
a) Pulling up the air sampling inlet cover
b) Changing the Mode 0 to BG
c) Pressing Start/Stop switch
d) Turning the knob to SENSI.ADJ and press it
e) Pressing Start/Stop switch again
f) Returning the knob to the position MEASURE slowly
g) Pressing the timer set switch to set measuring time
h) Removing the cap and start the measurement
Maintenance and Calibration for Direct Reading Dust Meter
2.2.15 ET shall submit
sufficient information to the IEC to prove that the instrument is capable of
achieving comparable results to the HVS. The instrument should also be
calibrated regularly, and the 1-hour sampling shall be determined periodically
by the HVS to check the validity and accuracy of the results measured by direct
reading method. The calibration certificate for the direct reading dust meter
is provided in Appendix C.
2.3 Construction
Noise Monitoring
Monitoring Requirement
2.3.1 In
accordance with the EM&A Manual, impact noise monitoring should be
conducted at the designated noise monitoring stations for at least once a week during
the construction phase of the Project. The parameters, frequency and duration
of impact noise monitoring is summarized in Table 2.3.
Table 2.3
Construction Noise Monitoring Parameters, Frequency and Duration
Parameter |
Duration |
Frequency |
A-weighted equivalent continuous sound pressure level (Leq). L10 and
L90 were also recorded |
30 minutes |
At least once per week |
Monitoring Equipment
2.3.2 Noise
monitoring was performed using sound level meter at the designated monitoring
station. The sound level meters deployed comply with the International
Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type
1) specifications. Acoustic calibrator was deployed to check the sound level
meters at a known sound pressure level.
2.3.3 The model
of the noise monitoring equipment used is summarized in Table 2.4.
Table 2.4 Construction
Noise Monitoring Equipment
Equipment |
Brand |
Model |
Serial No. |
Acoustic Calibrator |
Casella |
CEL-120/1 |
4358443 |
Sound Level Meter |
Casella |
CEL-63X |
4181568 |
Monitoring Methodology
2.3.4 Noise
measurement should be conducted as the following procedures:
a) Free field measurements was made at monitoring location M-N3. A
correction of +3 dB(A) shall be made to the free field measurements.
b) The battery condition should be checked to ensure good functioning of
the meter.
c) Parameters such as frequency weighting, the time weighting and the
measurement time should set as follow:
(i) Frequency
weighting: A
(ii) Time
weighting: Fast
(iii) Measurement
time: continuous 5 minutes interval
d) Prior to and after noise measurement, the meter shall be calibrated
using the calibrator for 94.0 dB at 1000 Hz. If the difference in the
calibration level before and after measurement is more than 1.0 dB, the
measurement will be considered invalid and repeat of noise measurement is
required after re-calibration or repair of the equipment.
e) The wind speed at the monitoring station shall be checked with the
portable wind meter. Noise monitoring should be cancelled in the presence of
fog, rain, and wind with a steady speed exceeding 5 m/s, or wind with gusts
exceeding 10 m/s.
f) Noise measurement should be paused during periods of high intrusive
noise if possible and observation shall be recorded when intrusive noise is not
avoided.
g) At the end of the monitoring period, the Leq, L10 and L90 should be
recorded. In addition, site conditions and noise sources should also be
recorded on a standard record sheet.
Maintenance and Calibration
2.3.5 Maintenance
and calibration procedures should also be carried out, including:
a) The microphone head of the sound level
meter and calibrator should be cleaned with a soft cloth at quarterly
intervals.
b) The sound level meter and calibrator
should be calibrated annually by a HOKLAS laboratory or the manufacturer.
The
calibration certificates for noise monitoring equipment are provided in Appendix D
2.4 Construction
Dust and Noise Monitoring Schedule
2.4.1 The
environmental monitoring schedule for the reporting period is provided in Appendix E.
2.5 The
Action and Limit Levels
2.5.1 The Action
and Limit Levels for construction dust and noise monitoring are provided in Appendix F.
2.6.1 As per the
EM&A Manuals, the landscape and visual mitigation measures shall be
implemented and site inspections should be undertaken once every two weeks
during the construction period. A summary of the implementation status is
presented in Section 4.
3. ENVIRONMENTAL MONITORING RESULTS
3.1 Construction
Dust Monitoring
3.1.1 The
monitoring results for 1-hour TSP and 24-hour TSP are summarized in Table
3.1 and Table 3.2
respectively. Detailed construction dust monitoring results and daily extract
of meteorological observations are presented in Appendix G.
Table 3.1 Summary
of 1-hour TSP Monitoring Results in the Reporting Period
Station ID |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
M-A3 |
57 |
38 ¡V 78 |
333 |
500 |
Table 3.2 Summary
of 24-hour TSP Monitoring Results in the Reporting Period
Station ID |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
M-A3 |
61 |
29 ¡V 90 |
153 |
260 |
3.1.2 No Action
and Limit Level exceedance was recorded for 1-hour TSP monitoring and 24-hour
TSP monitoring at the monitoring location in the reporting month.
3.1.3 Major dust
sources during the monitoring included nearby traffic emission.
3.1.4 The Event
and Action Plan for the construction dust monitoring is given in Appendix I.
3.2 Construction
Noise Monitoring
3.2.1 The
monitoring results for noise are summarized in Table 3.3
and the monitoring data is given in Appendix H.
Table 3.3 Summary
of Construction Noise Monitoring Results in the Reporting Period
Station ID |
1Measured
Noise Level, dB(A), Leq (30 mins) |
Action Level |
3Limit Level
dB(A), Leq (30 mins) |
M-N3 |
63.4¡V 69.8 |
When one documented
compliant is received |
For Schools: 70dB(A) during normal
teaching period and 65 dB(A) during examination periods |
Notes:
1. Free field noise levels were adjusted with a correlation of +3 dB(A);
3.2.2
No Action and Limit
Level exceedance was recorded for construction noise monitoring at the
monitoring location in the reporting month.
3.2.3
Major noise sources
during the monitoring included nearby traffic emission and school activities.
3.2.4 The Event
and Action Plan for the construction noise monitoring is given in Appendix I.
3.3.1 Auditing of
waste management practices during regular site inspections were confirmed that
the waste generated during construction were properly, stored, handled and
disposed of in general. The Contractor was responsible for the implementation
of any mitigation measures to reduce waste or redress issues arising from the
waste materials.
3.3.2 The
implemented environmental mitigation measures for the waste management in the
reporting period are summarized in Appendix J. The summary of
observations and recommendations made for waste management during the site
inspections are presented in Table 4.1
3.3.3 Monthly
summary of waste flow table is detailed in Appendix L.
3.4.1 Bi-weekly
inspection of the implementation of landscape and visual mitigation measures
were conducted on 14 and 29 January 2020. The implementation the landscape and
visual mitigation measures in the reporting period are summarized in Appendix J. The summary of
observations and recommendations made for landscape and visual mitigation
measures during the site inspections are presented in Table 4.1.
3.4.2 The Event
and Action Plan for landscape and visual during construction phase is given in Appendix
I.
4. ENVIRONMENTAL
SITE INSPECTION AND AUDIT
4.1 Site
inspections were carried out on a weekly basis to monitor the implementation of
proper environmental pollution control and mitigation measures for the Project.
A summary of the mitigation measures implementation status is provided in Appendix J.
4.1.2 In the
reporting month, five site inspections were carried out on 7, 14, 21 and 29
January 2020. Details of observations recorded during the site inspections are
presented in Table 4.1.
Table 4.1 Observations
and Recommendation of Site Inspection in the Reporting Period
Environmental
Aspect |
Date |
Observations
and Recommendations |
Follow-up
Actions |
1.
Air Quality |
14 Jan 2020 |
The Contractor was
remined to display the Non Road Mobile Machinery (NRMM) label for the drill
rig. |
The item was rectified by the Contractor on 20
Jan 2020. |
Noise |
14 Jan 2020 |
The breaker head should be covered with acoustic
mat. |
The item was rectified by the Contractor on 20
Jan 2020. |
Water
Quality |
Nil |
Nil |
Nil |
Waste
Management |
Nil |
Nil |
Nil |
Landscape
and Visual |
21 Jan 2020 |
The Contractor was remined to enhance the
protection of tree to remove the staking materials nearby. |
The item was rectified by the Contractor on 24
Jan 2020. |
Permit/
Licenses |
7 Jan 2020 |
The Contractor was remined to display the
Environmental Permit and relevant documents at the site entrance/ prominent
location. |
The item was rectified by the Contractor on 14
Jan 2020. |
5.
ENVIRONMENTAL COMPLAINT AND
NON-COMPLIANCE
Complaint Handling, Prosecution and Public
Engagement
5.1.1
No environmental
complaints, and no environmental related prosecutions or notification of
summons were received in the reporting period.
Cumulative complaint log, summaries of complaints, notification of
summons and successful prosecutions are presented in Appendix K.
No public engagement
activities were conducted in the reporting period.
Summary of Environmental Non-Compliance
5.1.2
No environmental
non-compliance was recorded in the reporting period.
5.1.3
No Action and Limit
Level exceedance was recorded for construction dust and noise monitoring in the
reporting month.
6. IMPLEMENTATION STATUS OF ENVIRONMENTAL MITIGATION MEASURE
6.1.1 The
Contractor had implemented environmental mitigation measures and requirements
as stated in the EIA Reports, the EP and EM&A Manuals. The implementation
status of the environmental mitigation measures during the reporting period is
summarized in Appendix
J.
Status of required submissions under the EP during the reporting period is
summarised in Table 6.1.
Table 6.1
Status of Required Submission under Environmental Permit
EP Condition |
Submission |
Submission
Date |
3.4 |
Monthly EM&A
Report (December 2019) |
14
January 2020 |
7. FUTURE KEY ISSUES
7.1.1 The main
works will be anticipated in the next reporting period are as follow:
¡P
Prebored
H piling for ventilation shaft;
¡P
Formation
of site haul road leading to Chung Hau Street;
¡P
Removal
of oversized tree extending to Chung Hau Street;
¡P
Initial
tunnel excavation for construction adit;
¡P
Mucking
out from tunnel;
¡P
Construction
of CLP transformer room;
¡P
Site
installation and utilities diversion;
¡P
Erection
of main site office.
7.1.2 The
recommended mitigation measures corresponding to the main works in the next
reporting period are listed as follow:
¡P
Mitigation
measures in form of regular watering under a good site practice should be
adopted, particularly for the earthwork and breaking activities;
¡P
Any
excavated, stockpile of dusty material or load of dusty materials on a vehicle
leaving a construction site should be covered entirely by impervious sheeting;
¡P
All
construction plants / machineries should be checked / serviced on a regular
basis during the courses of construction to minimize the emission of noise
generation and eliminate dark smoke emission;
¡P
All
C&D materials generated should be transported and stored at temporary
storage area. Suitable materials should be sorted for reuse on-site;
¡P
Wastewater
generated from drilling shall be properly collected for reuse or treated by
wastewater treatment facilities before discharge;
¡P
Provision
of drip trays for equipment likely cause spillage of chemical / fuel, and
provide routine maintenance;
¡P
Erecting
temporary noise barrier for noisy Powered Mechanical Equipment (PME) and
deployment of Quality Powered Mechanical Equipment (QPME) as many as
practicable;
¡P
Mitigation
measures recommended in the Landscape Mitigation Plan shall be implemented for
felling trees;
¡P
Conditions
in the Environmental Permit and License should be followed;
¡P
All
recommended mitigation measures specified in the approved EIA Report and
EM&A Manual shall be implemented.
7.1.3 The
environmental monitoring schedule for the next reporting month is provided in Appendix E.
8. CONCLUSION AND RECOMMENDATIONS
8.1.1 The 5th
Monthly EM&A Report for the Contract no. HY/2018/08 Central Kowloon Route ¡V
Central Tunnel summarized the monitoring results and audits findings of the
EM&A programme under the issued EP (EP No.: EP-457/2013/C) and in
accordance with the EM&A Manual during the reporting period from 01/01/2020
to 31/01/2020.
8.1.2
Construction
dust (including 1-hour and 24-hour TSP) and noise monitoring were carried out
in the reporting period. No Action and Limit Level exceedance was recorded for
construction dust and noise monitoring in the reporting month.
8.1.3
Weekly environmental
site inspections were conducted during the reporting period. In general, the
Contractor had implemented environmental mitigation measures and requirements
as stated in the EIA Reports, the EP and EM&A Manuals.
8.1.4
No environmental
complaints, and no environmental related prosecutions or notification of
summons were received in the reporting period.
8.1.5
No environmental
non-compliance was recorded in the reporting period.
8.1.6
According to the
environmental site inspections performed in the reporting month, the following
recommendations were provided:
Air Quality Impact
¡P
The Contractor was remined to display the
NRMM label for the drill rig.
Construction Noise Impact
¡P
The breaker head should be covered with
acoustic mat.
Water Quality Impact
¡P
No specific observation was identified in the
reporting month.
Waste Management
¡P
No specific observation was identified in the
reporting month.
Landscape and Visual Impact
¡P
The Contractor was remined to enhance the
protection of tree to remove the staking materials nearby.
Permit/ Licenses
¡P
The Contractor was remined to display the
Environmental Permit and relevant documents at the site entrance/ prominent
location.