This
is the 32nd Monthly EM&A Report prepared by Fugro
Technical Services Limited for the Contract No. HY/2018/08 Central Kowloon
Route ¡V Central Tunnel. The Contract No. HY/2018/08 commenced on 19 September
2019. This report summarized the monitoring results and audits findings of the
EM&A programme under the issued EP (EP No.: EP-457/2013/D) and in
accordance with the EM&A Manual during the reporting period from 01/04/2022
to 30/04/2022.
II.
Summary of Main Works Undertaken and Key Measures Implemented
The
main construction works carried out in the reporting period were as follow:
Ho Man Tin
¡P
Drill and blast excavation;
¡P
Tunnel mixed ground/ soft ground excavation;
¡P
Canopy and arch rib installation;
¡P
Tunnel smoothing works;
¡P
Mucking out from tunnel;
¡P
Modification of dewatering system;
¡P
Site and shaft Installation;
¡P
Site formation for pipe piling works;
¡P
Concreting for invert;
¡P
Assembly for waterproofing and lining gantry;
¡P
Tunnel Boring Machine (TBM) dismantling and removal.
Yau Ma Tei
¡P
Drill and break excavation;
¡P
Drill and blast excavation;
¡P
Canopy and arch rib installation;
¡P
Mucking out from tunnel;
¡P
Arch-rib installation;
¡P
Site and shaft installation.
Ma Tau Kok
¡P
Drill and blast excavation;
¡P
Mucking out from tunnel;
¡P
Tunnel Boring Machine (TBM) dismantling
and removal;
¡P
Site and shaft installation;
¡P
Installation of new ventilation
system;
¡P
Erection of utility tower and
passenger hoist.
Princess
Margaret Road
¡P
Reinstatement of planter.
Ka Tak
Barging Point
¡P
Spoil handling and disposal.
Sheung Lok
Street
¡P
Preparation for installation of
drop pipe.
III.
Summary of Exceedances, Investigation and Follow-up
No Action
and Limit Level exceedance was recorded for construction dust monitoring in the
reporting month.
Five
(5) Action Level exceedances were recorded for construction noise
due to the noise-related complaints received in the reporting month. No Limit
Level exceedance was recorded for construction noise monitoring in the
reporting month.
IV.
Complaint Handling, Prosecution and Public Engagement.
Six (6) noise-related complaints
were received in the last reporting month (i.e. 19, 20, 26,
28, 30 and 31 March 2022). The investigation reports for the complaints were
finalized on 10 May 2022.
Five (5) noise-related and
one air-related complaints (i.e. 7, 12, 13, 20, and 27 April 2022) were received
in the reporting month.
The complaint cases in March and April 2022
are summarized in Table I.
Table
I Environmental
Complaints Log
Complaint Log No. |
Date of Complaint |
Received From |
Nature of Complaint |
Status |
EC107_CKRCT20220319_395 |
19th March
2022 |
Contract Complaint
Hotline |
Construction Noise |
Investigation report
was finalized on 10 May 2022. |
EC108_CKRCT20220320_396 |
20th March
2022 |
Contract Complaint
Hotline |
Construction Noise |
Investigation report
was finalized on 10 May 2022. |
EC109_CKRCT20220326_402 |
26th March
2022 |
Contract Complaint
Hotline |
Construction Noise |
Investigation report
was finalized on 10 May 2022. |
EC110_CKRCT20220328_405 |
28th March
2022 |
Contract Complaint
Hotline |
Construction Noise |
Investigation report
was finalized on 10 May 2022. |
EC111_CKRCT20220330_406 |
30th March
2022 |
E-mail |
Construction Noise |
Investigation report
was finalized on 10 May 2022. |
EC112_CKRCT20220331_409 |
31st March
2022 |
Contract Complaint
Hotline |
Construction Noise |
Investigation report
was finalized on 10 May 2022. |
EC113_CKRCT20220407_413 |
7th April
2022 |
E-mail |
Construction Noise |
Under investigation
and the investigation results will be reported in the subsequent Monthly
EM&A Report. |
EC114_CKRCT20220412_416 |
12th April
2022 |
E-mail |
Construction Noise |
Under investigation
and the investigation results will be reported in the subsequent Monthly
EM&A Report. |
EC115_CKRCT20220413_418 |
13th April
2022 |
Contract Complaint
Hotline |
Air &
Construction Noise |
Investigation report
was finalized on 10 May 2022. |
EC116_CKRCT20220420_419 |
20th April
2022 |
E-mail |
Air |
Investigation report
was finalized on 10 May 2022. |
EC117_CKRCT20220427_424 |
27th April
2022 |
E-mail |
Construction Noise |
Under investigation
and the investigation results will be reported in the subsequent Monthly
EM&A Report. |
EC118_CKRCT20220427_425 |
27th April
2022 |
E-mail |
Construction Noise |
Under investigation
and the investigation results will be reported in the subsequent Monthly
EM&A Report. |
No
notification of summons and prosecutions were received in the reporting period.
No
public engagement activities were conducted in the reporting period.
V.
Reporting Change
There
were no reporting changes during the reporting month.
VI.
Future Key Issues
The
main works will be anticipated in the next reporting period are as follow:
Ho Man Tin
¡P
Drill and blast excavation;
¡P
Tunnel mixed ground/ soft ground excavation;
¡P
Canopy and arch rib installation;
¡P
Tunnel smoothing works;
¡P
Mucking out from tunnel;
¡P
Modification of dewatering system;
¡P
Site and shaft Installation;
¡P
Site formation for pipe piling works;
¡P
Concreting for invert;
¡P
Assembly for waterproofing and lining gantry;
¡P
Tunnel Boring Machine (TBM) dismantling and removal.
Yau Ma Tei
¡P
Drill and break excavation;
¡P
Drill and blast excavation;
¡P
Canopy and arch rib installation;
¡P
Mucking out from tunnel;
¡P
Arch-rib installation;
¡P
Site and shaft installation.
Ma Tau Kok
¡P
Drill and blast excavation;
¡P
Mucking out from tunnel;
¡P
Tunnel Boring Machine (TBM)
dismantling and delivery;
¡P
Site and shaft installation;
¡P
Installation of new ventilation
system;
¡P
Erection of utility tower and
passenger hoist.
Princess
Margaret Road
¡P
Reinstatement of planter.
Ka Tak
Barging Point
¡P
Spoil handling and disposal.
Sheung Lok
Street
¡P
Preparation for installation of
drop pipe.
The recommended
mitigation measures corresponding to the main works in the next reporting period
are listed as follow:
¡P
Good relationship shall be maintained with the nearby sensitive
receivers/ stakeholders which may be affected by the construction works such as
providing better/ more detail information of the work nature and inform in
advance of the works to the nearby residents;
¡P
Any excavated, stockpile of dusty material or load of dusty
materials on a vehicle leaving a construction site should be covered entirely
by impervious sheeting;
¡P
All construction plants / machineries should be checked / serviced
on a regular basis during the courses of construction to minimize the emission
of noise generation and eliminate dark smoke emission;
¡P
All C&D materials generated should be transported and stored at
temporary storage area. Suitable materials should be sorted for reuse on-site;
¡P
Every vehicle shall be cleaned thorough at the designated wheel
washing area onsite;
¡P
Wastewater generated from drilling shall be properly collected for
reuse or treated by wastewater treatment facilities before discharge;
¡P
Provision of drip trays for equipment likely cause spillage of
chemical / fuel, and provide routine maintenance;
¡P
Erecting temporary noise barrier for noisy Powered Mechanical
Equipment (PME) and deployment of Quality Powered Mechanical Equipment (QPME)
as many as practicable;
¡P
Conditions in the Environmental Permit and License should be
followed;
¡P
All recommended mitigation measures specified in the approved EIA
Report and EM&A Manual shall be implemented;
¡P
All vehicles should be cleaned
before leaving the construction site to ensure no muddy deposited by them on
roads.
The
following EP submissions were submitted during the reporting month:
Table II Status of Required Submission
under Environmental Permit
EP Condition |
Submission |
Submission Date |
3.4 |
Monthly EM&A Report (March 2022) |
14 April 2022 |
Contents
1.3 Construction Programme and Activities
1.4 Works undertaken during the month
1.5 Status of Environmental Licences, Notification and Permits
2.1 Construction Dust and Noise Monitoring Location
2.2 Construction Dust Monitoring
2.3 Construction Noise Monitoring
2.4 Construction Dust and Noise Monitoring Schedule
2.5 The Action and Limit Levels
3.1 Construction Dust Monitoring
3.2 Construction Noise Monitoring
5.1 Complaint Handling, Prosecution and Public Engagement
5.2 Summary of Environmental Non-Compliance
5.3 Summary of Monitoring Exceedance
Tables
Table I ¡V Environmental
Complaints Log
Table II ¡V Status of Required Submission under
Environmental Permit
Table 1.1 ¡V Contact Information of Key
Personnel
Table 1.2 ¡V Environmental Licenses,
Notification and Permits Summary
Table 2.1 ¡V Construction Dust and Noise
Monitoring Location
Table 2.2 ¡V Construction Dust Monitoring
Equipment
Table 2.3 ¡V Construction Noise Monitoring
Parameters, Frequency and Duration
Table 2.4 ¡V Construction Noise Monitoring
Equipment
Table 3.1 ¡V Summary of 1-hour TSP Monitoring Results
in the Reporting Period
Table 3.2 ¡V Summary of 24-hour TSP Monitoring
Results in the Reporting Period
Table 3.3 ¡V Summary of Construction Noise
Monitoring Results in the Reporting Period
Table 4.1 ¡V Observations and Recommendation
of Site Inspection in the Reporting Period
Table 5.1 ¡V Environmental Complaints Log
Table 6.1 ¡V Status of Required Submission
under Environmental Permit
Figures
Figure 1 The Site Layout Plan of the Contract
Figure
2.1 The Location of the Construction Dust and Noise Monitoring Stations
(Ho Man Tin)
Figure
2.2 The Location of the Construction Dust and Noise Monitoring Stations (Ma
Tau Kok)
Figure 2.3 The Location of the Construction Dust and Noise Monitoring Stations (Yau Ma Tei)
Appendices
Appendix A Construction
Programme
Appendix B Project Organization Chart
Appendix C Calibration Certificate for
Construction Dust Monitoring Equipment
Appendix D Calibration Certificate for
Construction Noise Monitoring Equipment
Appendix E Environmental Monitoring
Schedule
Appendix F Action and Limit Levels for Construction
Dust and Noise Monitoring
Appendix G Construction Dust Monitoring Results
and Meteorological Observations
Appendix H Construction Noise Monitoring
Results
Appendix I Event and Action Plan
Appendix J Implementation Status of
Environment Mitigation Measures (Construction Phase)
Appendix K Cumulative Statistics on
Exceedances, Complaints, Notifications of Summons and Successful Prosecutions
Appendix L Waste
Flow Table
Table 1.1
Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Highways Department (HyD) |
E13/CKR |
Mr. Joe Lam |
2762 3380 |
Arup-Mott MacDonald Joint Venture (AMMJV) |
Senior Resident Engineer |
Mr. Ben Poon |
3619 5967 |
ERM-Hong Kong, Limited (ERM) |
Independent Environmental
Checker (IEC) |
Ms. Mandy To |
2271 3000 |
Bouygues Travaux Publics (BTP) |
Environmental Manager |
Mr. Simon Wong |
9281 4346 |
Fugro Technical
Services Limited |
ET Leader |
Mr. David Hung |
3565 4371 |
¡P
Drill and blast excavation;
¡P
Tunnel mixed ground/ soft ground excavation;
¡P
Canopy and arch rib installation;
¡P
Tunnel smoothing works;
¡P
Mucking out from tunnel;
¡P
Modification of dewatering system;
¡P
Site and shaft Installation;
¡P
Site formation for pipe piling works;
¡P
Concreting for invert;
¡P
Assembly for waterproofing and lining gantry;
¡P
Tunnel Boring Machine (TBM) dismantling and removal.
Yau Ma Tei
¡P
Drill and break
excavation;
¡P
Drill and blast excavation;
¡P
Canopy and arch rib installation;
¡P
Mucking out from tunnel;
¡P
Arch-rib installation;
¡P
Site and shaft installation.
Ma Tau Kok
¡P
Drill and blast excavation;
¡P
Mucking out from tunnel;
¡P
Tunnel Boring Machine (TBM)
dismantling and removal;
¡P
Site and shaft installation;
¡P
Installation of new ventilation
system;
¡P
Erection of utility tower and
passenger hoist.
Princess Margaret Road
¡P
Reinstatement of planter.
Ka Tak Barging Point
¡P
Spoil handling and disposal.
Sheung Lok Street
¡P
Preparation for installation of
drop pipe.
Table 1.2 Environmental
Licenses, Notification and Permits Summary
Permit/
Notification/ License |
Reference No |
Valid From |
Valid Till |
Form NB |
448930,
448970, 448971 |
Mid-Sep
2019 |
NA |
Billing Account for Disposal
of C&D waste |
Account
no. 7034790 |
06 Aug 2019 |
NA |
Chemical Waste Producer
Registration (Ho Man Tin Construction site) |
5111-236-B2557-02 |
25
Sep 2019 |
NA |
Chemical Waste Producer
Registration (Yau Ma Tei
Construction site) |
5213-225-B2557-05 |
19
Apr 2021 |
NA |
Chemical Waste Producer
Registration (Ma Tau Kok Construction site) |
5213-247-B2557-06 |
19 Apr 2021 |
NA |
Construction Noise Permit |
|||
Construction
Noise Permit (Ho Man Tin Construction site) |
GW-RE0017-22 |
14 Jan 2022 |
13 May 2022 |
Construction
Noise Permit (Yau Ma Tei
Construction site) |
GW-RE0192-22 |
07 Mar 2022 |
06 May 2022 |
Construction Noise Permit (Ma
Tau Kok Construction site) |
GW-RE0091-22 |
04 Feb 2022 |
03 Apr 2022 |
Construction Noise Permit (Ma
Tau Kok Construction site) |
GW-RE0288-22 |
04 Apr 2022 |
03 Aug 2022 |
Construction Noise Permit (Kai Tak
Barging Point) |
GW_RE0182-22 |
08 Mar 2022 |
02 Sep 2022 |
Construction Noise Permit
(Drilling & Grouting at Chi Man Street ¡V 19:00-23:00) |
GW-RE0968-21 |
06 Oct 2021 |
05 Apr 2022 |
Water Discharge License |
|||
Water Discharge License |
WT00034873-2019
(Ho Man Tin Construction site) |
22 Nov 2019 |
30 Nov 2024 |
WT00035436-2019 (Portion 18) |
02 Apr 2020 |
30 Apr 2025 |
|
WT00037723-2021 (Yau Ma Tei
Construction site) |
07 Apr 2021 |
30 Apr 2026 |
|
WT00037883-2021 (Ma Tau Kok Construction site) |
30 Apr 2021 |
30 Apr 2026 |
Table 2.1
Construction Dust and Noise Monitoring Locations
Dust Monitoring Station ID |
Noise Monitoring Station ID |
Monitoring Location |
M-A3 |
M-N3 |
SKH Tsoi Kung Po Secondary School |
/ |
E-N12a |
19 Hing Yan Street |
E-A14a |
E-N21a |
Block B of Merit Industrial Centre |
W-A6 |
/ |
Man Cheong building |
/ |
W-N18 |
Hydan Place |
/ |
W-N25A |
Prosperous Garden Block 1 |
Notes:
1. The dust and noise monitoring
stations proposed in the EM&A Manual for M-A6/ M-N6 (i.e. Ko Fai House, Kwun Fai Court) was
not available for impact dust and noise monitoring, therefore impact monitoring
was conducted at M-A3/ M-N3 as an alternative which was agreed by the ER, IEC
and EPD;
2. The noise monitoring station proposed
in the EM&A Manual for E-N12 (i.e. Grand Waterfront Tower 3) was not
available for impact dust and noise monitoring, therefore impact monitoring was
conducted at E-N12a as an alternative which was agreed by the ER, IEC and EPD;
3. The dust and noise monitoring
stations proposed in the EM&A Manual for E-A14 (i.e. Wyler Gardens) and E-N21 (i.e Hang Chien Court Block J) was
not available for impact dust and noise monitoring, therefore impact monitoring
was conducted at E-A14a/ E-N21a as an alternative which was agreed by the ER,
IEC and EPD;
4. The dust monitoring stations
proposed in the EM&A Manual for W-A5 (i.e. The Coronation) was not
available for impact dust monitoring, therefore impact monitoring was conducted
at W-A6 as an alternative which was agreed by the ER, IEC and EPD.
Monitoring Requirement
Monitoring Equipment
Table 2.2 Construction
Dust Monitoring Equipment
Equipment |
Brand |
Model |
Serial No. |
High
Volume Sampler (24-hour TSP) |
Tisch |
TE-5170 |
4388 |
Calibrator |
Tisch |
TE-5025A |
2456 |
Portable direct reading dust meter (1-hour TSP) |
Sibata |
LD-5R |
155717 |
Monitoring Methodology
for HVS
¡P
Sufficient support is provided to secure the samplers against gusty
wind.
¡P
No two samplers are placed less than 2 meters apart.
¡P
The distance between the sampler and an obstacle, such as
buildings, is at least twice the height that the obstacle protrudes above the
sampler.
¡P
A minimum of 2 meters of separation from walls, parapets and
penthouses is required for rooftop samples.
¡P
A minimum of 2 meters separation from any supporting structure,
measured horizontally is required.
¡P
No furnaces or incineration flues are nearby.
¡P
Airflow around the samplers is unrestricted.
¡P
The samplers are more than 20 meters from the drip line.
¡P
Any wire fence and gate, to protect the sampler, should not cause
any obstruction during monitoring.
¡P
Permission must be obtained to set up the samplers and to obtain
access to the monitoring stations.
¡P
A secured supply of electricity is needed to operate the samplers.
Maintenance
and Calibration for HVS
Monitoring Methodology
for Direct Reading Dust Meter
a) Pulling up
the air sampling inlet cover
b) Changing the
Mode 0 to BG
c) Pressing
Start/Stop switch
d) Turning the
knob to SENSI.ADJ and press it
e) Pressing
Start/Stop switch again
f) Returning
the knob to the position MEASURE slowly
g) Pressing the
timer set switch to set measuring time
h) Removing the
cap and start the measurement
Maintenance
and Calibration for Direct Reading Dust Meter
Monitoring
Requirement
Table 2.3
Construction Noise Monitoring Parameters, Frequency and Duration
Parameter |
Duration |
Frequency |
A-weighted
equivalent continuous sound pressure level (Leq).
L10 and L90 were also recorded |
30 minutes |
At least once
per week |
Monitoring Equipment
Table 2.4 Construction
Noise Monitoring Equipment
Equipment |
Brand |
Model |
Serial No. |
Acoustic Calibrator |
Casella |
CEL-120/1 |
5230758 |
Sound Level Meter |
Casella |
CEL-63X |
1488293 |
Monitoring Methodology
a) Free field
measurements was made at monitoring location M-N3. A correction of +3 dB(A) shall be made to the free field measurements.
b) The battery
condition should be checked to ensure good functioning of the meter.
c) Parameters
such as frequency weighting, the time weighting and the measurement time should
set as follow:
(i) Frequency
weighting: A
(ii) Time weighting: Fast
(iii) Measurement time: 30 minutes
d) Prior to and
after noise measurement, the meter shall be calibrated using the calibrator for
94.0 dB at 1000 Hz. If the difference in the calibration level before and after
measurement is more than 1.0 dB, the measurement will be considered invalid and
repeat of noise measurement is required after re-calibration or repair of the
equipment.
e) The wind
speed at the monitoring station shall be checked with the portable wind meter.
Noise monitoring should be cancelled in the presence of fog, rain, and wind
with a steady speed exceeding 5 m/s, or wind with gusts exceeding 10 m/s.
f) Noise
measurement should be paused during periods of high intrusive noise if possible
and observation shall be recorded when intrusive noise is not avoided.
g) At the end
of the monitoring period, the Leq, L10 and L90 should
be recorded. In addition, site conditions and noise sources should also be
recorded on a standard record sheet.
Maintenance
and Calibration
a) The microphone head of the sound
level meter and calibrator should be cleaned with a soft cloth at quarterly
intervals.
b) The sound level meter and
calibrator should be calibrated annually by a HOKLAS laboratory or the
manufacturer.
The
calibration certificates for noise monitoring equipment are provided in Appendix
D.
Table 3.1 Summary
of 1-hour TSP Monitoring Results in the Reporting Period
Station ID |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
M-A3 |
58 |
45-72 |
333 |
500 |
Table 3.2 Summary
of 24-hour TSP Monitoring Results in the Reporting Period
Station ID |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
M-A3 |
58 |
32-88 |
153 |
260 |
Table 3.3 Summary
of Construction Noise Monitoring Results in the Reporting Period
Station ID |
1Measured Noise Level, dB(A), Leq (30 mins) |
1 2Corrected Noise Level, dB(A), Leq (30 mins)
|
Action
Level |
3Limit Level dB(A), Leq
(30 mins) |
M-N3 |
66.8-68.4 |
56.2 |
When one documented compliant
is received |
For Schools: 70dB(A) during normal teaching
period and 65 dB(A) during examination periods |
Notes:
1. Free field noise levels
were adjusted with a correlation of +3 dB(A);
2. Corrected Noise Level =10*
log (10^ (Measured Noise Level/10) ¡V 10^ (Baseline Noise Level/10)), where the
Baseline Noise Level = 67.7 dB(A).
3.
The Limit Level was 70 dB(A) for teaching period (from 1 to 23 April
2022) and 65 dB(A) for examination period (from 22 to 30 April 2022)
Table 4.1 Observations
and Recommendation of Site Inspection in the Reporting Period
Environmental
Aspect |
Date |
Observations
and Recommendations |
Follow-up
Actions |
Air Quality |
12th April 2022 |
-The Contractor was reminded to provide wheel washing for the dump
truck to minimize the dust impact. |
-The item was rectified by the Contractor on 19th April
2022. |
26th April 2022 |
-The Contractor was reminded to replace the NRMM labels for the
PMEs. |
-The item was rectified by the Contractor on 3rd May
2022. |
|
Noise |
Nil |
Nil |
Nil |
Water Quality |
Nil |
Nil |
Nil |
Waste Management |
Nil |
Nil |
Nil |
Landscape and Visual |
Nil |
Nil |
Nil |
Permit/ Licenses |
Nil |
Nil |
Nil |
Table 5.1 Environmental
Complaints Log
Complaint Log No. |
Date of Complaint |
Received From |
Nature of Complaint |
Status |
EC107_CKRCT20220319_395 |
19th March
2022 |
Contract Complaint
Hotline |
Construction Noise |
Investigation report
was finalized on 10 May 2022. |
EC108_CKRCT20220320_396 |
20th March
2022 |
Contract Complaint
Hotline |
Construction Noise |
Investigation report
was finalized on 10 May 2022. |
EC109_CKRCT20220326_402 |
26th March
2022 |
Contract Complaint
Hotline |
Construction Noise |
Investigation report
was finalized on 10 May 2022. |
EC110_CKRCT20220328_405 |
28th March
2022 |
Contract Complaint
Hotline |
Construction Noise |
Investigation report
was finalized on 10 May 2022. |
EC111_CKRCT20220330_406 |
30th March
2022 |
E-mail |
Construction Noise |
Investigation report
was finalized on 10 May 2022. |
EC112_CKRCT20220331_409 |
31st March
2022 |
Contract Complaint
Hotline |
Construction Noise |
Investigation report
was finalized on 10 May 2022. |
EC113_CKRCT20220407_413 |
7th April
2022 |
E-mail |
Construction Noise |
Under investigation
and the investigation results will be reported in the subsequent Monthly
EM&A Report. |
EC114_CKRCT20220412_416 |
12th April
2022 |
E-mail |
Construction Noise |
Under investigation
and the investigation results will be reported in the subsequent Monthly
EM&A Report. |
EC115_CKRCT20220413_418 |
13th April
2022 |
Contract Complaint
Hotline |
Air &
Construction Noise |
Investigation report
was finalized on 10 May 2022. |
EC116_CKRCT20220420_419 |
20th April
2022 |
E-mail |
Air |
Investigation report
was finalized on 10 May 2022. |
EC117_CKRCT20220427_424 |
27th April
2022 |
E-mail |
Construction Noise |
Under investigation
and the investigation results will be reported in the subsequent Monthly
EM&A Report. |
EC118_CKRCT20220427_425 |
27th April
2022 |
E-mail |
Construction Noise |
Under investigation
and the investigation results will be reported in the subsequent Monthly
EM&A Report. |
Table 6.1
Status of Required Submission under Environmental Permit
EP Condition |
Submission |
Submission Date |
3.4 |
Monthly EM&A Report (March 2022) |
14 April 2022 |
Ho Man
Tin
¡P
Drill and blast excavation;
¡P
Tunnel mixed ground/ soft ground excavation;
¡P
Canopy and arch rib installation;
¡P
Tunnel smoothing works;
¡P
Mucking out from tunnel;
¡P
Modification of dewatering system;
¡P
Site and shaft Installation;
¡P
Site formation for pipe piling works;
¡P
Concreting for invert;
¡P
Assembly for waterproofing and lining gantry;
¡P
Tunnel Boring Machine (TBM) dismantling and removal.
Yau Ma Tei
¡P
Drill and break excavation;
¡P
Drill and blast excavation;
¡P
Canopy and arch rib installation;
¡P
Mucking out from tunnel;
¡P
Arch-rib installation;
¡P
Site and shaft installation.
Ma Tau Kok
¡P
Drill and blast excavation;
¡P
Mucking out from tunnel;
¡P
Tunnel Boring Machine (TBM)
dismantling and delivery;
¡P
Site and shaft installation;
¡P
Installation of new ventilation
system;
¡P
Erection of utility tower and
passenger hoist.
Princess Margaret Road
¡P
Reinstatement of planter.
Ka Tak Barging Point
¡P
Spoil handling and disposal.
Sheung Lok Street
¡P
Preparation for installation of
drop pipe.
¡P
Good relationship shall be maintained with the nearby sensitive
receivers/ stakeholders which may be affected by the construction works such as
providing better/ more detail information of the work nature and inform in
advance of the works to the nearby residents;
¡P
Any excavated, stockpile of dusty material or load of dusty
materials on a vehicle leaving a construction site should be covered entirely
by impervious sheeting;
¡P
All construction plants / machineries should be checked / serviced
on a regular basis during the courses of construction to minimize the emission
of noise generation and eliminate dark smoke emission;
¡P
All C&D materials generated should be transported and stored at
temporary storage area. Suitable materials should be sorted for reuse on-site;
¡P
Every vehicle shall be cleaned thorough at the designated wheel
washing area onsite;
¡P
Wastewater generated from drilling shall be properly collected for
reuse or treated by wastewater treatment facilities before discharge;
¡P
Provision of drip trays for equipment likely cause spillage of
chemical / fuel, and provide routine maintenance;
¡P
Erecting temporary noise barrier for noisy Powered Mechanical
Equipment (PME) and deployment of Quality Powered Mechanical Equipment (QPME)
as many as practicable;
¡P
Conditions in the Environmental Permit and License should be
followed;
¡P
All recommended mitigation measures specified in the approved EIA
Report and EM&A Manual shall be implemented.
¡P
All vehicles should be cleaned
before leaving the construction site to ensure no muddy deposited by them on
roads.
Air Quality Impact
¡P
The Contractor was reminded to
provide wheel washing for the dump truck to minimize the dust impact.
¡P
The Contractor was reminded to
replace the NRMM labels for the PMEs.
Construction Noise Impact
¡P
No specific observation was
identified in the reporting month.
Water Quality Impact
¡P
No specific observation was
identified in the reporting month.
Waste Management
¡P
No specific observation was
identified in the reporting month.
Landscape and Visual Impact
¡P
No specific observation was
identified in the reporting month.
Permit/ Licenses
¡P
No specific observation was
identified in the reporting month.