Table of Contents
2.......... Project Information
2.3 Construction Programme and
Activities
2.5 Status of Environmental Licences,
Notification and Permits
3.......... Environmental Monitoring
Requirements
3.1 Construction Dust Monitoring
3.2 Construction Noise Monitoring
4.......... Implementation
Status of Environmental Mitigation Measures
5.......... Monitoring
Results
5.1 Construction Dust Monitoring
5.2 Regular Construction Noise
Monitoring
6.......... ENVIRONMENTAL
SITE INSPECTION AND AUDIT
6.2 Summary of Monitoring Exceedances
6.3 Summary of Environmental
Non-Compliance
6.4 Summary of Environmental Complaints
6.5 Summary of Environmental Summon and
Successful Prosecutions
7.1 Construction Programme for the Next
Three Month
7.2 Key Issues for the Coming Month
7.3 Monitoring Schedule for the Coming
Month
8.......... ConclusionS AND
RECOMMENDATIONS
List of Tables
Table
2.1........... Construction Activities in the
reporting month
Table
2.2........... Contact
Information of Key Personnel
Table
2.3........... Status
of Environmental Licenses, Notifications and Permits
Table
3.1........... Air Quality Monitoring Equipment
Table
3.2........... Location of Construction Dust Monitoring Station
Table
3.3........... Noise
Monitoring Parameters, Frequency and Duration
Table
3.4........... Noise Monitoring Equipment for Regular Noise
Monitoring
Table
3.5........... Noise
Monitoring Stations during Construction Phase
Table
3.6........... Noise
Monitoring Parameters, Frequency and Duration
Table
4.1........... Status of Required Submission under
Environmental Permit
Table
5.1........... Summary
of 24-hour TSP Monitoring Result in the Reporting Period
Table
5.2........... Summary
of 1-hour TSP Monitoring Result in the Reporting Period
Table
5.3........... Summary
of Construction Noise Monitoring Results in the Reporting Period
Table
6.1........... Observations
and Recommendations of Site Audit
Table
7.1........... Construction Activities in the
coming three month
List of Figures
Site Layout Plan |
|
Location of Air Quality Monitoring Station |
|
Locations of Noise Monitoring Station |
List
of Appendices
Construction Programme |
|
Project Organization Structure |
|
Implementation Schedule of Environmental Mitigation Measures |
|
Summary of Action and Limit Levels |
|
Calibration Certificates of Equipment |
|
EM&A Monitoring Schedules |
|
Air Quality Monitoring Results and their Graphical Presentations |
|
Noise Monitoring Results and their Graphical Presentations |
|
Event and Action Plan |
|
Cumulative Statistics on Complaints, Notification of Summons and
Successful Prosecutions |
|
Monthly Summary Waste Flow Table |
Central Kowloon Route
– Kai Tak West (CKR-KTW; Contract No. HY/2014/07) (hereafter called “the
Project”) covers part of the construction of the Central Kowloon Route (CKR).
The Project comprises
the follow works:
·
50x30m
access shaft with noise enclosure at Ma Tau Kok
(MTK);
·
100m long
cut-and-cover (C&C) tunnel at MTK;
·
Demolition
and re-provisioning of MTK Public Pier;
·
160m long
underwater tunnel (UWT) (Stage 1);
·
210m long
UWT (Stage 2);
·
60m long
C&C tunnel at Kai Tak;
·
130m long
depressed road and 200m long underpass at Kai Tak;
·
390m long
underground tunnel ventilation adit at Kai Tak;
·
Seawall
demolition and construction of new landing steps; and
·
Barging
Point enclosure and conveyor system.
The EM&A programme commenced on 4 April 2018.The impact EM&A for the Project includes
air quality and noise monitoring.
This is the
twenty-fifth monthly EM&A Report presenting the EM&A works carried out
during the period between 1 and 30 April 2020. As informed by the Contractor, major activities in the
reporting period were:
Locations |
Site Activities |
Kai Tak |
·
Excavation and ELS installation at cut & cover tunnel,
depressed road and underpass; ·
Construction of New Right of Way; ·
Temporary Grouting |
Ma Tau Kok |
·
TTM implementation; ·
Pipe piling works for cut and cover tunnel; ·
Rock Excavation; ·
ELS installation & Access platform concreting works; ·
Existing drainage diversion works; ·
Laying of lighting ducts; ·
Excavation at Covered Walkway |
Kowloon Bay |
·
Excavation for Stage 1 underwater tunnel; ·
S2 Truss fabrication and installation; ·
Temporary Grouting; ·
Pumping Test |
Barging Point |
·
Barging point operation (Spoil Disposal) |
Breaches of Action and Limit Levels for Air Quality
All 24-hour TSP result was below the Action
and Limit Levels at all monitoring locations in the reporting month.
All 1-hour TSP result was below the Action and
Limit Levels at all monitoring locations in the reporting month.
Breaches of Action and Limit Levels for Noise
Regular Noise Monitoring
No Action Level exceedance was recorded since no noise related complaint was received in the reporting month.
No
exceedance of Limit Level of noise was recorded in the reporting month.
Complaint, Notification of Summons and Successful Prosecution
One (1)
complaint received by Highway Department on 14 April 2020 for dust and referred
by the Contractor on 17 April 2020, the investigation report was
finalized on 28 April 2020.
No notification
of summons and successful prosecution were received in the reporting month.
Reporting Changes
There was no
reporting change in the reporting month.
Future Key Issues
Key issues to be
considered in the next three months included:
Locations |
Site Activities |
Kai Tak |
·
Base slab and wall, roof slab construction at underpass and
depressed road; ·
Excavation and ELS installation at cut & cover tunnel,
depressed road and underpass; ·
Temporary Grouting; ·
Backfilling works and ELS removal at Underpass |
Ma Tau Kok |
·
TTM implementation; ·
Rock excavation; ·
ELS installation and Access platform concreting works; ·
Pipe piling works for cut and cover tunnel; ·
Laying of lighting ducts at Metered Carpark area; ·
Fresh water pipe installation works; ·
Covered walkway construction |
Kowloon Bay |
·
Excavation for stage 1 underwater tunnel; ·
S4 - S6 ELS installation; ·
Temporary Grouting; ·
Backfilling and ELS removal works; ·
Blinding layer, base slab and wall construction |
Barging Point |
·
Barging point operation (Spoil Disposal) |
·
Section 1:
Introduction
·
Section 2:
Project Information
·
Section 3:
Environmental Monitoring Requirement
·
Section 4:
Implementation Status of Environmental Mitigation Measures
·
Section 5:
Monitoring Results
·
Section 6:
Environmental Site Inspection and Audit
·
Section 7: Environmental Non-conformance
·
Section 8:
Future Key Issues
·
Section 9:
Conclusions and Recommendations
(a) construction of approximately 160m long cut-and-cover tunnel and
370m long underwater tunnel between the tunnel section at Ma Tau Kok and the depressed road of the CKR within Kai Tak
Development;
(b) reconstruction of the seawall at Ma Tau Kok
public pier, and the sloping seawall at the Former Kai Tak Airport Runway;
(c) construction of approximately 125m long depressed road and 200m
long underpass of the CKR within Kai Tak Development;
(d) construction of approximately 360m long underground tunnel
ventilation adit of the CKR;
(e) reconstruction of Kowloon City Ferry Pier Public Transport
Interchange; and
(f) other associated works.
Table 2.1 Construction Activities in the reporting month
Locations |
Site Activities |
Kai
Tak |
·
Excavation and ELS installation at cut & cover tunnel,
depressed road and underpass; ·
Construction of New Right of Way; ·
Temporary Grouting |
Ma
Tau Kok |
·
TTM implementation; ·
Pipe piling works for cut and cover tunnel; ·
Rock Excavation; ·
ELS installation & Access platform concreting works; ·
Existing drainage diversion works; ·
Laying of lighting ducts; ·
Excavation at Covered Walkway |
Kowloon
Bay |
·
Excavation for Stage 1 underwater tunnel; ·
S2 Truss fabrication and installation; ·
Temporary Grouting; ·
Pumping Test |
Barging
Point |
·
Barging point operation (Spoil
Disposal) |
Table 2.2 Contact Information of Key Personnel
Party |
Role |
Position |
Name |
Telephone |
Fax |
Arup-Mott
MacDonald Joint Venture |
Residential
Engineer (ER) |
Engineer’s
Representative |
Mr. Jeffrey
Lau |
2268 3640 |
2268 3954 |
ERM |
Independent Environmental
Checker (IEC) |
Independent
Environmental Checker |
Ms. Mandy To |
2271 3313 |
2723 5660 |
Gammon |
Contractor |
Contracts Manager |
Mr. Alan Yan |
2516 8823 |
2516 6260 |
Environmental Manager |
Ms Michelle Tang |
9267 8866 |
|||
AECOM |
Contractor’s Environmental
Team (ET) |
ET Leader |
Mr. Y T Tang |
3922 9392 |
2317 7609 |
Table 2.3 Status of Environmental Licenses, Notifications and Permits
Permit / License No. / Notification/
Reference No. |
Valid Period |
Status |
Remarks |
|
From |
To |
|||
Further
Environmental Permit |
||||
FEP-01/457/2013/C |
28 Feb 2018 |
End of Project |
Valid |
-- |
Wastewater
Discharge License |
||||
WT00030290-2018 |
22 Mar 2018 |
31 Mar 2023 |
Valid |
Ma Tau Kok |
WT00030668-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Site Office at
Kai Tak West |
WT00030358-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Kai Tak West |
WT00030333-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Barging Point
at Portions 4B & 4C |
WT00030330-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Kowloon Bay |
Construction
Noise Permit |
||||
GW-RE0108-20 |
6 Mar
2020 |
26 Aug 2020 |
Valid |
Barging Point
Operation at Kai Tak Barging Point |
GW-RE1013-19 |
17 Dec 2019 |
16 Apr 2020 |
Valid until 16
Apr 2020 |
Rock Breaking
at Ma Tau Kok |
GW-RE0201-20 |
16 Apr 2020 |
15 Jul 2020 |
Valid on 16
Apr 2020 |
|
GW-RE0986-19 |
6 Dec 2019 |
1 Jun 2020 |
Valid |
General Works
at Kai Tak |
GW-RE1012-19 |
17 Dec 2019 |
12 Jun 2020 |
Valid |
Welding and
backfilling at Stage 1 Underwater Tunnel |
GW-RE0254-20 |
9 Apr 2020 |
30 Sep 2020 |
Valid on 9 Apr
2020 |
Kai Tak Haul
Road |
Chemical Waste Producer Registration |
||||
5118-247-G2347-47 |
30 Jan 2018 |
End of Project |
Valid |
-- |
5118-247-G2347-48 |
30 Jan 2018 |
End of Project |
Valid |
-- |
Marine Dumping Permit |
||||
EP/MD/20-048 |
16 Oct 2019 |
15 Apr 2020 |
Valid until 15 Apr 2020 |
Sediments requiring Type 1 - Open Sea Disposal |
EP/MD/20-143 |
16 Apr 2020 |
30 Jun 2020 |
Valid on 16 Apr 2020 |
|
EP/MD/20-134 |
6 Mar 2020 |
5 Apr 2020 |
Valid until 5 Apr 2020 |
Sediments requiring Type 1 (Dedicated Site) and Type 2 Confined Marine
Disposal |
EP/MD/20-142 |
6 Apr 2020 |
5 May 2020 |
Valid on 6 Apr 2020 |
|
Billing
Account for Construction Waste Disposal |
||||
7029909 |
22 Jan 2018 |
End of Project |
Account Active |
-- |
7031949 |
26 Feb 2020 |
26 May 2020 |
Account Active |
Billing Account for Disposal of
Construction Waste (by vessels) |
Notification
Under Air Pollution Control (Construction Dust) Regulation |
||||
429442 |
5 Jan 2018 |
5 Jul 2025 |
Notified |
-- |
Monitoring Requirements
Monitoring Equipment
Table 3.1 Air Quality Monitoring Equipment
Tisch
Total Suspended Particulate Mass Flow Controlled High Volume Air Sampler |
|
Portable
direct reading dust meter |
Sibata Digital Dust Monitor |
Monitoring Locations
Table 3.2 Location of Construction Dust Monitoring Station
Location |
Monitoring Station |
Description |
E-A14a
[1] |
Block
B of Merit Industrial Centre |
Rooftop
(13/F) |
[1] The air monitoring station
proposed in the EM&A Manual (i.e. Wyler Gardens with ID: E-A14) was not
available for impact dust monitoring, therefore impact monitoring was conducted
at E-A14a as an alternative which was agreed by the ER, IEC and EPD.
Monitoring
Methodology
(a)
The HVS
was installed in the vicinity of the air sensitive receivers. The following criteria were considered in the
installation of the HVS as far as practicable: -
(i)
A horizontal platform with
appropriate support to secure the sampler against gusty wind was provided.
(ii)
Two samplers should
not be placed less than 2m apart from each other;
(iii)
The distance between the HVS and
any obstacles, such as buildings, was at least twice the height that the
obstacle protrudes above the HVS.
(iv)
A minimum of 2 meters separation
from walls, parapets and penthouse for rooftop sampler.
(v)
A minimum of 2 meters separation
from any supporting structure, measured horizontally is required.
(vi)
No furnace or incinerator flues
nearby.
(vii)
Airflow around the sampler was
unrestricted.
(viii)
The sampler was located more than
20 meters from any dripline.
(ix)
Any wire fence and gate, required
to protect the sampler, did not obstruct the monitoring process.
(x)
Permission was obtained to set up
the samplers and access to the monitoring station.
(xi)
A secured supply of electricity
was obtained to operate the sampler.
(b)
Preparation
of Filter Papers
(i)
Glass fibre filters, G810 were
labelled and sufficient filters that were clean and
without pinholes were selected.
(ii)
All filters were equilibrated in
the conditioning environment for 24 hours before weighing. The conditioning
environment temperature was around 25 °C and not variable by more than ±3 °C;
the relative humidity (RH) was < 50% and not variable by more than ±5%. A
convenient working RH was 40%.
(iii)
All filter papers were prepared
and analysed by ALS Technichem (HK) Pty Ltd., which is a HOKLAS accredited
laboratory and has comprehensive quality assurance and
quality control programmes.
(c)
Field
Monitoring
(i)
The power
supply was checked to ensure the HVS works properly.
(ii)
The filter holder and the area
surrounding the filter were cleaned.
(iii)
The filter holder was removed by
loosening the four bolts and a new filter, with stamped number upward, on a
supporting screen was aligned carefully.
(iv)
The filter was properly aligned
on the screen so that the gasket formed an airtight seal on the outer edges of
the filter.
(v)
The swing bolts were fastened to
hold the filter holder down to the frame.
The pressure applied was sufficient to avoid
air leakage at the edges.
(vi)
Then the shelter lid was closed
and was secured with the aluminium strip.
(vii)
The HVS was warmed-up for about 5
minutes to establish run-temperature conditions.
(viii)
A new flow rate record sheet was
set into the flow recorder.
(ix)
On site temperature and
atmospheric pressure readings were taken and the flow rate of the HVS was
checked and adjusted at around 1.3 m3/min, and
complied with the range specified in the EM&A Manual (i.e. 0.6-1.7 m3/min).
(x)
The programmable digital timer
was set for a sampling period of 24 hrs, and the starting time, weather
condition and the filter number were recorded.
(xi)
The initial elapsed time was
recorded.
(xii)
At the end of sampling, on site
temperature and atmospheric pressure readings were taken and the final flow
rate of the HVS was checked and recorded.
(xiii)
The final elapsed time was
recorded.
(xiv)
The sampled filter was removed
carefully and folded in half length so that only
surfaces with collected particulate matter were in contact.
(xv)
It was then placed in a clean
envelope and sealed.
(xvi)
All monitoring information was
recorded on a standard data sheet.
(xvii) Filters were then sent to ALS Technichem (HK) Pty Ltd. for analysis.
(d)
Maintenance
and Calibration
(i)
The HVS and its accessories were maintained in good working condition, such as
replacing motor brushes routinely and checking electrical wiring to ensure a
continuous power supply.
(ii)
HVSs were calibrated using
TE-5025A Calibration Kit upon installation and thereafter at bi-monthly
intervals.
(iii)
Calibration certificate of the TE-5025A Calibration Kit and the HVSs are provided in
Appendix E.
(a)
Measuring Procedures
The measuring procedures of the 1-hour dust
meter are in accordance with the Manufacturer’s Instruction Manual as follows:
(i)
Turn the power on.
(ii)
Close the air collecting opening cover.
(iii)
Push the “TIME SETTING” switch to [BG]
(iv)
Push “START/STOP”
switch to perform background measurement for 6 seconds.
(v)
Turn the knob at SENSI ADJ position to insert
the light scattering plate.
(vi)
Leave the equipment for 1 minute upon “SPAN
CHECK” is indicated in the display.
(vii)
Push “START/STOP” switch to perform automatic
sensitivity adjustment. This measurement takes 1 minute.
(viii)
Pull out the knob and return it to MEASURE
position.
(ix)
Push the “TIME SETTING” switch the time set
in the display to 3 hours.
(x)
Lower down the air collection opening cover.
(xi)
Push “START/STOP” switch to start
measurement.
(b)
Maintenance and
Calibration
(i)
The 1-hour TSP meter was
calibrated at 1-year intervals against a continuous particulate TEOM Monitor,
Series 1400ab. Calibration certificates of the Laser Dust Monitors are
provided in Appendix E.
Monitoring Schedule for the
Reporting Month
Monitoring Requirements
Table 3.3 Noise Monitoring Parameters, Frequency and Duration
Parameter and Duration |
Frequency |
30-mins
measurement at each monitoring station between 0700 and 1900 on normal
weekdays. Leq, L10 and L90
would be recorded. |
At least once per week |
Table 3.4 Noise Monitoring Equipment for Regular Noise Monitoring
B&K (Model No. 2238) |
|
Acoustic
Calibrator |
MVI (Model No.
CAL21) |
Monitoring Locations
Table 3.5 Noise Monitoring Stations during Construction Phase
Location |
Monitoring Station |
Description |
Measurement |
E-N12a [1] |
19 Hing Yan Street |
Rooftop (9/F) |
Façade |
E-N21a [1] |
Block B of Merit Industrial Centre |
Rooftop (13/F) |
Free field [2] |
Notes:
[1] The noise monitoring stations proposed in
the EM&A Manual (i.e. Grand Waterfront Tower 3 with ID: E-N12 and Hang Chien Court Block J with ID: E-N21) were not available for
impact noise monitoring, therefore impact monitoring was conducted at E-N12a
and E-N21a as an alternative which was
agreed by the ER, IEC and EPD.
[2] A
correction of +3 dB(A) was made to the free field measurements.
Monitoring
Parameters, Frequency and Duration
Table 3.6 Noise Monitoring Parameters, Frequency and Duration
Location |
Parameter and Duration |
Frequency |
E-N12a and E-N21a |
30-mins measurement at each
monitoring station between 0700 and 1900 on normal weekdays. Leq, L10 and L90 would
be recorded. |
At
least once per week |
Monitoring Methodology
(a)
The sound level meter was set on
a tripod at a height of 1.2 m above the ground.
(b)
Façade measurement was made at
E-N12a.
(c)
Free field measurements was made at monitoring location E-N21a. A correction of +3
dB(A) shall be made to the free field measurements.
(d)
The battery condition was checked to ensure the correct
functioning of the meter.
(e)
Parameters such as frequency weighting,
the time weighting and the measurement time were set as follows:
(i)
frequency weighting: A
(ii)
time weighting: Fast
(iii)
time measurement: Leq(30-minutes) during non-restricted
hours i.e. 0700 – 1900 on normal weekdays.
(f)
Prior to and after each noise
measurement, the meter was calibrated using the acoustic calibrator for 94
dB(A) at 1000 Hz. If the difference in
the calibration level before and after measurement was more than 1 dB(A), the
measurement would be considered invalid and repeat of noise measurement would
be required after re-calibration or repair of the equipment.
(g)
During the monitoring period, the
Leq, L10 and L90
were recorded. In addition, site
conditions and noise sources were recorded on a standard record sheet.
(h)
Noise measurement was paused during
periods of high intrusive noise (e.g. dog barking, helicopter noise) if
possible. Observations were recorded when intrusive noise was unavoidable.
(i)
Noise monitoring was cancelled in
the presence of fog, rain, wind with a steady speed exceeding 5m/s, or wind
with gusts exceeding 10m/s.
(a)
The
microphone head of the sound level meter was cleaned with soft
cloth at regular intervals.
(b)
The meter
and calibrator were sent to the supplier or HOKLAS laboratory to check and
calibrate at yearly intervals.
(c)
Calibration
certificates of the sound level meters and acoustic calibrators are
provided in Appendix
E.
Monitoring Schedule for the Reporting Month
Table 4.1 Status of Required Submission under Environmental Permit
EP Condition |
Submission |
Submission
Date |
Condition 3.4 of |
Monthly EM&A Report
for March 2020 |
14 April 2020 |
Table 5.1 Summary of 24-hour
TSP Monitoring Result in the Reporting Period
ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
E-A14a |
44.0 |
26.7 – 64.2 |
197.3 |
260 |
Table 5.2 Summary of 1-hour TSP Monitoring Result in the Reporting Period
ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
E-A14a |
61.3 |
59.7 – 63.3 |
302.4 |
500 |
Table 5.3 Summary of Construction Noise Monitoring Results in the Reporting Period
ID |
Range, dB(A), Leq (30 mins) |
Limit Level, dB(A), Leq (30 mins) |
E-N12a |
65.7
– 67.7 |
75 |
E-N21a |
65.0
– 69.4 |
75 |
l Excavation profiles
must be properly designed and executed.
l Stockpiling site(s)
shall be lined with impermeable sheeting and bunded. Stockpiles shall be fully
covered by impermeable sheeting to reduce dust emission.
l Excavation and
stockpiling should be carried out during dry season as far as possible to
minimise potentially contaminated runoffs from the Concerned Soil.
l Regular site audit
will be conducted under the Environmental Monitoring and Audit (EM&A) programme
to ensure the soil excavation, stockpiling and backfilling works are carried
out in accordance with this report.
Findings of the site audit will be presented in Table 6.1.
l The truck
transferring Concerned Soil shall be covered entirely by impervious sheeting to
ensure that the dusty materials do not leak from the truck.
Table 6.1 Observations and
Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Air
Quality |
29 April
2020 |
· Haul road at the Steel Platform was observed dry. The Contractor was
advised to provide water spraying regularly on the haul road for dust
suppression. |
This item will
be followed up in next reporting period. |
Reminder: ·
The Contractor was
reminded to replace the decolored NRMM label on the
excavator at the Steel Platform. |
This item will
be followed up in next reporting period. |
||
Noise |
1
April 2020 |
· Acoustic mat was
not erected around the generator at Ma Tau Kok. The
Contractor was reminded to erect the acoustic mat around the generator for
noise screening. |
The item was
rectified on 3 Apr 2020. |
Water
Quality |
15 April 2020 |
· Gaps was observed at the silt curtain near the Steel Platform. The
Contractor was reminded to seal the gap to maintain the effectiveness of silt
curtain. |
The item was
rectified on 21 Apr 2020. |
Reminder: ·
The Contractor was
reminded to seal the hole of the drip tray at Ma Tau Kok
to maintain the effectiveness of oil interception. |
The item was
rectified on 16 Apr 2020. |
||
22 April 2020 |
·
Oil stain was observed
on the ground at Kai Tak. The Contractor was reminded to clean up the oil
stain in timely manner. |
The item was
rectified on 24 Apr 2020. |
|
29
April 2020 |
· Canvas was not
erected properly during the material transference at the Steel Platform. The Contractor was reminded to erect the canvas properly
to prevent silt material drop into the sea. |
This item will be
followed up in next reporting period. |
|
Waste/
Chemical Management |
1
April 2020 |
· General refuse was observed rested near the seawall and accumulated in
the receptacle at the Steel Platform and underpass area of Kai Tak. The
Contractor was reminded to remove the general refuse regularly for site
tidiness. |
The item was
rectified on 6 Apr 2020. |
8
April 2020 |
·
Domestic waste was
observed without proper handling at underpass of Kai Tak. The Contractor was
reminded to provide proper handling for the domestic waste. |
The item was
rectified on 11 Apr 2020. |
|
·
Overflow of waste was
observed at the receptacle in Kai Tak Barging Point. The Contractor was
reminded to remove the waste regularly to maintain the site tidiness. |
The item was
rectified on 10 Apr 2020. |
||
15 April 2020 |
·
Overflow of waste was
observed inside the receptacle at Kai Tak. The Contractor was reminded to
remove the waste regularly to maintain the site tidiness. |
The item was
rectified on 17 Apr 2020. |
|
Land
Contamination |
Nil |
Nil |
Nil |
Landscape &
Visual |
Nil |
Nil |
Nil |
Permits/ Licenses |
Nil |
Nil |
Nil |
Table 7.1 Construction Activities in the coming three months
Locations |
Site Activities |
Kai
Tak |
·
Base slab and wall, roof slab construction at underpass and
depressed road; ·
Excavation and ELS installation at cut & cover tunnel,
depressed road and underpass; ·
Temporary Grouting; ·
Backfilling works and ELS removal at Underpass |
Ma
Tau Kok |
·
TTM implementation; ·
Rock excavation; ·
ELS installation and Access platform concreting works; ·
Pipe piling works for cut and cover tunnel; ·
Laying of lighting ducts at Metered Carpark area; ·
Fresh water pipe installation works; ·
Covered walkway construction |
Kowloon
Bay |
·
Excavation for stage 1 underwater tunnel; ·
S4 - S6 ELS installation; ·
Temporary Grouting; ·
Backfilling and ELS removal works; ·
Blinding layer, base slab and wall construction |
Barging
Point |
·
Barging point operation (Spoil
Disposal) |